Share Cane Parkway Road Reconstruction on FacebookShare Cane Parkway Road Reconstruction on TwitterShare Cane Parkway Road Reconstruction on LinkedinEmail Cane Parkway Road Reconstruction link
The Town of Newmarket is making infrastructure improvements and road reconstruction on Cane Parkway as it is reaching the end of its useful life. Work is expected to begin in Summer 2027 and completed by Summer 2028.
Work includes, but is not limited to:
Replacement of the watermain, sanitary sewer and storm sewer
Lane reconfiguration to improve traffic flow and accommodate parking needs
Implementation of Low Impact Development (LID) features to manage stormwater
Construction of a Multi-Use Path (MUP) on the east side to connect to the Mulock MUP and the Tom Taylor Trail
Installation of a new sidewalk on the west side adjacent to Dennis Park
Installation of a pedestrian refuge island across from Dennis Park to improve crossing safety
Retention of existing centre median islands, where feasible
New tree plantings to enhance Newmarket’s urban tree canopy
Parking lot enhancements
Installation of new street lighting
Road reconstruction, including new asphalt paving
Public Consultation Centre (PCC): Cane Parkway Road Reconstruction Project
The Town of Newmarket invites residents to attend a drop-in for a Public Consultation Centre (PCC) to learn more about the Cane Parkway Road Reconstruction.
When: Tuesday, April 21, 2026, from 6 to 8 p.m.
Where: Municipal Offices (395 Mulock Drive) in the Cane A & Cane B Rooms
Drop by anytime to review the design, ask questions and provide feedback. Representatives from the Town’s Engineering Services will be available to answer questions.
The Town of Newmarket is making infrastructure improvements and road reconstruction on Cane Parkway as it is reaching the end of its useful life. Work is expected to begin in Summer 2027 and completed by Summer 2028.
Work includes, but is not limited to:
Replacement of the watermain, sanitary sewer and storm sewer
Lane reconfiguration to improve traffic flow and accommodate parking needs
Implementation of Low Impact Development (LID) features to manage stormwater
Construction of a Multi-Use Path (MUP) on the east side to connect to the Mulock MUP and the Tom Taylor Trail
Installation of a new sidewalk on the west side adjacent to Dennis Park
Installation of a pedestrian refuge island across from Dennis Park to improve crossing safety
Retention of existing centre median islands, where feasible
New tree plantings to enhance Newmarket’s urban tree canopy
Parking lot enhancements
Installation of new street lighting
Road reconstruction, including new asphalt paving
Public Consultation Centre (PCC): Cane Parkway Road Reconstruction Project
The Town of Newmarket invites residents to attend a drop-in for a Public Consultation Centre (PCC) to learn more about the Cane Parkway Road Reconstruction.
When: Tuesday, April 21, 2026, from 6 to 8 p.m.
Where: Municipal Offices (395 Mulock Drive) in the Cane A & Cane B Rooms
Drop by anytime to review the design, ask questions and provide feedback. Representatives from the Town’s Engineering Services will be available to answer questions.