The Town of Newmarket is making infrastructure improvements and road reconstruction on Cane Parkway as it is reaching the end of its useful life. Work is expected to begin in Spring 2027 and completed by Summer 2029.
Work includes, but is not limited to:
Replacement of the watermain, sanitary sewer and storm sewer
Lane reconfiguration to improve traffic flow and accommodate parking needs
Implementation of Low Impact Development (LID) features to manage stormwater
Construction of a Multi-Use Path (MUP) on the east side to connect to the Mulock MUP and the Tom Taylor Trail
Installation of a new sidewalk on the west side adjacent to Dennis Park
Installation of a pedestrian refuge island across from Dennis Park to improve crossing safety
Retention of existing centre median islands, where feasible
New tree plantings to enhance Newmarket’s urban tree canopy
Parking lot enhancements
Installation of new street lighting
Road reconstruction, including new asphalt paving
The Town of Newmarket is making infrastructure improvements and road reconstruction on Cane Parkway as it is reaching the end of its useful life. Work is expected to begin in Spring 2027 and completed by Summer 2029.
Work includes, but is not limited to:
Replacement of the watermain, sanitary sewer and storm sewer
Lane reconfiguration to improve traffic flow and accommodate parking needs
Implementation of Low Impact Development (LID) features to manage stormwater
Construction of a Multi-Use Path (MUP) on the east side to connect to the Mulock MUP and the Tom Taylor Trail
Installation of a new sidewalk on the west side adjacent to Dennis Park
Installation of a pedestrian refuge island across from Dennis Park to improve crossing safety
Retention of existing centre median islands, where feasible
New tree plantings to enhance Newmarket’s urban tree canopy
Share Sign-up to receive email updates for Cane Parkway Reconstruction on FacebookShare Sign-up to receive email updates for Cane Parkway Reconstruction on X (formerly Twitter)Share Sign-up to receive email updates for Cane Parkway Reconstruction on LinkedinEmail Sign-up to receive email updates for Cane Parkway Reconstruction link
Page last updated: 09 Oct 2026, 02:23 PM
Residents interested in receiving key project updates are encouraged to subscribe to receive email updates on this project. Project updates will also be provided in the construction update section on this webpage.
Cane Parkway Road Reconstruction has finished this stage
The Town hosted a Public Consultation Centre (PCC) on April 21, 2026, to provide information about the project and gather feedback from the community. The presentation boards from the PCC are available on this project webpage for review.
Public Information Centre
Cane Parkway Road Reconstruction is currently at this stage
The Town is planning to host a Public Information Centre in early 2027. Additional details, including the date, time and location, will be shared as they become available.
Project Construction
this is an upcoming stage for Cane Parkway Road Reconstruction
Construction is anticipated to begin in Spring 2027.
Project Completion
this is an upcoming stage for Cane Parkway Road Reconstruction
Construction is anticipated to be completed by Summer 2029.