May 14, 2025 - Phase 2 Notice of Construction
This notice is to inform you that construction of the Mulock Drive Multi-Use Path Phase 2 will begin the week on May 12th, 2025. The project will be completed in phases along Mulock Drive between Yonge Street and Harry Walker Parkway and is anticipated to be finished by Spring 2026.
What to Expect
Construction will occur in phases, the first phase being Yonge Street to Sandford Street
on the north side of Mulock Drive
The curbside lane adjacent to the work area will be occupied during construction
Pedestrian detour signs will be installed and maintained throughout the project
Access to businesses will remain open at all times
Construction Impacts
Typical work hours will be from Monday to Friday, 7 a.m. – 7 p.m.
Curbside lane closures are permitted only between 9:30 a.m. – 3:30 p.m.
Some work may occur on weekends and overnight, depending on construction
requirements.
Advance notice will be provided for any significant access changes or restrictions.
Project Benefits
The Mulock Drive Multi-Use Path project is a Council-endorsed project that supports Newmarket’s Extraordinary Places and Spaces priority. It will enhance Mulock Drive’s vibrancy and will allow for a wide-range of recreational uses such as cycling, walking, jogging, and access for all abilities, while improving connections to parks, schools, trails, and the future Mulock Park—advancing the Town’s goal of a more sustainable and connected community.
We appreciate your patience during construction of the path. Project updates will be shared as construction progresses.