October 2026

Additional Field Work

Complete the remaining field work (e.g., surveying, tree inventory verification) to support the preferred detailed design.

November 05 2026

Public Meeting

Host a hybrid meeting (e.g., in-person and online format) with adjacent residents to review the preferred design in detail, provide project updates, and discuss any additional questions or concerns.

December 2026

Public Meeting (Tentative)

Host an additional hybrid meeting (e.g. in-person and online) with adjacent residents to review any changes resulting from the November meeting. 

January 2027

Final Design

Final design completed and preparation of construction tender package.

February 2027

Tree Removals

Tree removals, subject to environmental timing requirements.

March 2027

Construction Tender

Construction tendering and contractor procurement.

July 2027

Construction

Anticipated start of construction, subject to approvals, procurement, environmental timing windows and weather conditions.