Complete the remaining field work (e.g., surveying, tree inventory verification) to support the preferred detailed design.
November 05 2026
Public Meeting
Host a hybrid meeting (e.g., in-person and online format) with adjacent residents to review the preferred design in detail, provide project updates, and discuss any additional questions or concerns.
December 2026
Public Meeting (Tentative)
Host an additional hybrid meeting (e.g. in-person and online) with adjacent residents to review any changes resulting from the November meeting.
January 2027
Final Design
Final design completed and preparation of construction tender package.
February 2027
Tree Removals
Tree removals, subject to environmental timing requirements.
March 2027
Construction Tender
Construction tendering and contractor procurement.
July 2027
Construction
Anticipated start of construction, subject to approvals, procurement, environmental timing windows and weather conditions.