Project Updates

Project Update #3 - August 14, 2025:

  • Crews have set up temporary traffic signals to assist with traffic control. Please use caution when driving through the site.

  • Crews have also begun setting up the temporary watermain.

We appreciate your patience and will continue to provide updates as the project progresses.


Project Update #2 - August 12, 2025:

  • Crews will be onsite in the coming days to start setting up temporary watermain

  • Following the temporary watermain setup, pits will be dug to access the watermain

  • Commencement of watermain lining work following pit excavation

We appreciate your patience and will continue to provide updates as the project progresses.


Project Update #1 - July 23, 2025

We’re excited to share that work is scheduled to begin in approximately 2-3 weeks. Here’s what to expect in the early stages of the project:

  • Installation and commissioning of the temporary watermain

  • Excavation of watermain lining pits

  • Commencement of watermain lining work following pit excavation

We appreciate your patience and will continue to provide updates as the project progresses.


Share Project Updates on Facebook Share Project Updates on Twitter Share Project Updates on Linkedin Email Project Updates link
#<Object:0x00007ff418559998>