Project Updates
Project Update #3 - August 14, 2025:
Crews have set up temporary traffic signals to assist with traffic control. Please use caution when driving through the site.
Crews have also begun setting up the temporary watermain.
We appreciate your patience and will continue to provide updates as the project progresses.
Project Update #2 - August 12, 2025:
Crews will be onsite in the coming days to start setting up temporary watermain
Following the temporary watermain setup, pits will be dug to access the watermain
Commencement of watermain lining work following pit excavation
We appreciate your patience and will continue to provide updates as the project progresses.
Project Update #1 - July 23, 2025
We’re excited to share that work is scheduled to begin in approximately 2-3 weeks. Here’s what to expect in the early stages of the project:
Installation and commissioning of the temporary watermain
Excavation of watermain lining pits
Commencement of watermain lining work following pit excavation
We appreciate your patience and will continue to provide updates as the project progresses.

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends