Bristol Road Watermain Lining Project
Consultation has concluded
We are pleased to share the successful completion of Bristol Road Watermain Lining and Road Resurfacing project as of June 2026.
The project included full lining of existing watermain line and services connection, followed by asphalt restoration. This project significantly improves water service reliability for residents and reduces the need for future maintenance.
Construction was completed by North Rock Group on budget, with design and contract administration provided by Ainley Group.
We thank residents for their patience during construction and acknowledge all project partners for their contributions to this successful delivery.
We are pleased to share the successful completion of Bristol Road Watermain Lining and Road Resurfacing project as of June 2026.
The project included full lining of existing watermain line and services connection, followed by asphalt restoration. This project significantly improves water service reliability for residents and reduces the need for future maintenance.
Construction was completed by North Rock Group on budget, with design and contract administration provided by Ainley Group.
We thank residents for their patience during construction and acknowledge all project partners for their contributions to this successful delivery.
-
Notice of Construction Restart - May 12, 2026
Share Notice of Construction Restart - May 12, 2026 on Facebook Share Notice of Construction Restart - May 12, 2026 on X (formerly Twitter) Share Notice of Construction Restart - May 12, 2026 on Linkedin Email Notice of Construction Restart - May 12, 2026 linkRoad Resurfacing of Bristol Road
May 12, 2026
Bristol Road project is scheduled to resume on the week of May 19, 2026. The Contractor, North Rock Group Ltd, will be returning to complete remaining works including final concrete works, asphalt paving, line painting and boulevard restorations, with on-site inspection provided by Ainley& Associates Limited.
Construction Works
The following works will take place on Bristol Road, from Main Street North to 40m past Chester Ave during this time:
• Curb and sidewalk repairs
• Grinding of existing asphalt
• Final asphalt paving
• Road line painting
• Boulevard and property restorations including topsoil and sod (where required)
What to Expect
• Work will typically occur Monday to Friday, 7 a.m. – 7 p.m.
• Occasional weekend and/or night work may be required.
• Temporary driveway and on-street parking restrictions may occur.
• Short-term access disruptions will be coordinated in advance.
• Emergency Services and waste collection will continue to have access.
• The road will be limited to local traffic only with detours in-place during asphalt paving operations.
The project is anticipated to be completed by June 2026. The Town of Newmarket appreciates your cooperation and patience as we complete this important infrastructure project. Further updates will be provided as work progresses.
Consultation has concludedRoad Resurfacing of Bristol Road
May 12, 2026
Bristol Road project is scheduled to resume on the week of May 19, 2026. The Contractor, North Rock Group Ltd, will be returning to complete remaining works including final concrete works, asphalt paving, line painting and boulevard restorations, with on-site inspection provided by Ainley& Associates Limited.
Construction Works
The following works will take place on Bristol Road, from Main Street North to 40m past Chester Ave during this time:
• Curb and sidewalk repairs
• Grinding of existing asphalt
• Final asphalt paving
• Road line painting
• Boulevard and property restorations including topsoil and sod (where required)
What to Expect
• Work will typically occur Monday to Friday, 7 a.m. – 7 p.m.
• Occasional weekend and/or night work may be required.
• Temporary driveway and on-street parking restrictions may occur.
• Short-term access disruptions will be coordinated in advance.
• Emergency Services and waste collection will continue to have access.
• The road will be limited to local traffic only with detours in-place during asphalt paving operations.
The project is anticipated to be completed by June 2026. The Town of Newmarket appreciates your cooperation and patience as we complete this important infrastructure project. Further updates will be provided as work progresses.
-
Project Update
Share Project Update on Facebook Share Project Update on X (formerly Twitter) Share Project Update on Linkedin Email Project Update linkProject Update #4 - September 4, 2025:
Completed work so far includes utility locates, traffic control setup, test pits for investigation, and setting up the temporary watermain
The team is currently testing and commissioning the temporary watermain to ensure it is safe and potable.
Once testing is complete, all homes will be transferred to the temporary watermain. Hoses will run above ground from the temporary watermain to the outside hose taps during this process.
After all water services have been switched, the existing watermain will be shut down, and construction of the lining pits will begin.
We appreciate your patience and will continue to provide updates as the project progresses.
Consultation has concludedProject Update #4 - September 4, 2025:
Completed work so far includes utility locates, traffic control setup, test pits for investigation, and setting up the temporary watermain
The team is currently testing and commissioning the temporary watermain to ensure it is safe and potable.
Once testing is complete, all homes will be transferred to the temporary watermain. Hoses will run above ground from the temporary watermain to the outside hose taps during this process.
After all water services have been switched, the existing watermain will be shut down, and construction of the lining pits will begin.
We appreciate your patience and will continue to provide updates as the project progresses.
-
AG
Phone 905-953-5300 x 2595 Email agjylbegaj@newmarket.ca
-
Pre-Construction Meeting
Bristol Road Watermain Lining Project has finished this stage -
Site Setup - August 2025
Bristol Road Watermain Lining Project has finished this stage -
Construction
Bristol Road Watermain Lining Project has finished this stage -
Site Cleanup and Restoration
Bristol Road Watermain Lining Project has finished this stage -
Project Completion - October 2025
Bristol Road Watermain Lining Project is currently at this stage
Residents interested in receiving key project updates are encouraged to subscribe to receive email updates on this project. Project updates will also be provided in the construction update section on this webpage.




