Kingdale Road Culvert Replacement Project

Share Kingdale Road Culvert Replacement Project on Facebook Share Kingdale Road Culvert Replacement Project on Twitter Share Kingdale Road Culvert Replacement Project on Linkedin Email Kingdale Road Culvert Replacement Project link

About the Project

The Town of Newmarket is upgrading its stormwater management facility on Kingdale Road (see map for details) so they can continue to protect the community and the environment from stromwater runoff created by rain and snow melt events.

The Town has retained Ainley Group as its consultants for the design of the project which has been completed and is currently out for tender to secure a contractor. Once a contractor has been selected, this project is expected to begin in October 2023 with an estimated completion date of December 2023 (weather and site condition dependent).

In order to facilitate this project, some utilities (Hydro, Enbridge Gas and Bell Canada) near Mulock Drive will need to be relocated. Hydro and Enbridge utility relocations have been complete with Bell Canada currently on-site and on schedule to complete their relocations soon.

As with all construction projects, the Town of Newmarket will work with the contractor to minimize disruptions to residents in the area as much as possible.

We thank you for your patience and understanding as we work to maintain strong and healthy infrastructure that will prevent flooding and pollution of fresh water resources and protect aquatic habitats and the environment.

Map of Construction Area


Contact:

Should you have any questions regarding the project, please reach out to Hossam Mossa, Project Manager, Capital Projects, at the Town of Newmarket by emailing hmossa@newmarket.ca or by calling 905-895-5193 ext. 2504.

About the Project

The Town of Newmarket is upgrading its stormwater management facility on Kingdale Road (see map for details) so they can continue to protect the community and the environment from stromwater runoff created by rain and snow melt events.

The Town has retained Ainley Group as its consultants for the design of the project which has been completed and is currently out for tender to secure a contractor. Once a contractor has been selected, this project is expected to begin in October 2023 with an estimated completion date of December 2023 (weather and site condition dependent).

In order to facilitate this project, some utilities (Hydro, Enbridge Gas and Bell Canada) near Mulock Drive will need to be relocated. Hydro and Enbridge utility relocations have been complete with Bell Canada currently on-site and on schedule to complete their relocations soon.

As with all construction projects, the Town of Newmarket will work with the contractor to minimize disruptions to residents in the area as much as possible.

We thank you for your patience and understanding as we work to maintain strong and healthy infrastructure that will prevent flooding and pollution of fresh water resources and protect aquatic habitats and the environment.

Map of Construction Area


Contact:

Should you have any questions regarding the project, please reach out to Hossam Mossa, Project Manager, Capital Projects, at the Town of Newmarket by emailing hmossa@newmarket.ca or by calling 905-895-5193 ext. 2504.

  • Project Progress Update during the week of Nov. 13, 2023

    Share Project Progress Update during the week of Nov. 13, 2023 on Facebook Share Project Progress Update during the week of Nov. 13, 2023 on Twitter Share Project Progress Update during the week of Nov. 13, 2023 on Linkedin Email Project Progress Update during the week of Nov. 13, 2023 link

    During the last week (the week of Nov. 6) , the Contractor completed the following:

    1. All the concrete works (culvert installation and distribution slab).
    2. The distribution slab's water proofing.

    During this week (the week of Nov. 13), the contractor shall complete the following:

    1. All the backfilling around the culvert and on the top of the culvert.
    2. Road restoration (granular subbase, base layer of asphalt, top layer of asphalt and the street lines).
    3. The top soil at road both sides.
    4. General cleaning and demobilization.

    Our plans to have the road re-opened for normal traffic early next week.

  • Project Progress Update during the week of October 23, 2023

    Share Project Progress Update during the week of October 23, 2023 on Facebook Share Project Progress Update during the week of October 23, 2023 on Twitter Share Project Progress Update during the week of October 23, 2023 on Linkedin Email Project Progress Update during the week of October 23, 2023 link
    supporting image

    During the week of October 23, 2023, the Contractor completed the following:

    1. Set-up the Traffic Control Plan,
    2. Mobilization and site planning,
    3. Excavate and remove the old culvert, and
    4. New culvert installation.

    During the coming week of October 30, 2023, the Contractor will do:

    1. Backfilling, and
    2. Distribution slab


  • Notice of Construction - October 2023

    Share Notice of Construction - October 2023 on Facebook Share Notice of Construction - October 2023 on Twitter Share Notice of Construction - October 2023 on Linkedin Email Notice of Construction - October 2023 link

    The Town of Newmarket will be making improvements to the stormwater system in your neighborhood. The Town has awarded a contract to Ambler & Co. to replace the existing steel stormwater culvert on Kingdale Road that is nearing its end of life and replace it with a concrete box culvert. (See map below) The goal of this project is to renew the existing stormwater infrastructure to mitigate potential flooding. Construction work is scheduled to commence on October 23, 2023, and is expected to last until November 30, 2023, depending on weather and other unforeseeable circumstances.

    The Town is trying to minimize the impacts that will be felt by residents during construction. However, please note the following:

    ROAD CLOSURE: Kingdale Road will be closed in both directions at the culvert location near the Mulock Drive intersection throughout the construction. As a result, access to your home will be from Leslie Street only. Detour signage will be installed to direct the general public, including delivery services. All Emergency Services are being notified so that they are aware of the change and therefore, emergency response times will not be affected.

    GARBAGE COLLECTION: Residents north of Druery Court will be provided with black bags for garbage and clear bags for recycling and green bin waste. Garbage and recycling will be collected on your normal scheduled pickup days at your curbside by the Contractor. While residents are encouraged to use the bags provided, recycling bins can still be used, but they must be labeled with your address so that they can be returned to your home after pickup. Residents are asked to have garbage/recycling at the end of their driveway by 7:00 a.m. on pick-up day. For residents south of Druery Court and on Druery Court, your garbage and recycling pickup routines will not be affected.

    COMMUNITY MAILBOX: Canada Post has relocated the current mailbox south of the construction site to the west side of Kingdale Road to allow for safe and more convenient access for residents during construction. The mailbox will be returned to its original location at the end of construction.

    Construction projects of this nature usually cause some degree of dust, noise, and vibration. The Town and its contractor will make every effort to minimize these inconveniences as much as possible. We appreciate your patience during the construction.

    We also understand that children may be curious about the construction activities and equipment, so we kindly ask parents to keep children and pets out of the construction areas, both during and after working hours. The usual working hours are between 7:00 a.m. to 7:00 p.m., Monday to Friday. There could be work on some Saturdays, but this would be on occasion only.

    The Town of Newmarket encourages your comments and inquiries about the project. Should you have any questions regarding the project prior to or during the work, please reach out to Hossam Mossa, Project Manager, Capital Projects, at the Town of Newmarket by emailing hmossa@newmarket.ca or by calling 905-895-5193 ext. 2504. After hours emergencies can be reported to the Town’s Customer Service by calling 905-895-5193.

    We thank you for your patience and understanding during this work.

    Regards,

Page last updated: 20 Feb 2024, 11:28 AM