Key Dates
Phase 3 of the project begins
May 8th to 14th: Work will be completed at the intersection of Lorne Avenue and Park Avenue.
May 15th to 21st: Work will be completed at the intersection of Lorne Avenue and Millard Avenue.
May 22nd to 28th: Work will be completed at the intersection of Lorne Avenue and Queen Street.
Lorne Avenue - Road Closure (Eagle Street - Davis Drive)
Lorne Avenue will be closed from Eagle Street to Davis Drive to non-resident traffic as of June 16, 2022 for construction until September 1st, 2022. During this time, only residents and emergency services will be allowed access at all times.
Virtual Public Information Centre for the Lorne Avenue Reconstruction Project
A Public Information Centre was hosted on March 16, 2021 for residents to learn more about the design and technical aspect of the project.