May 01 2023

Phase 3 of the project begins

May 8th to 14th: Work will be completed at the intersection of Lorne Avenue and Park Avenue.

May 15th to 21st: Work will be completed at the intersection of Lorne Avenue and Millard Avenue.

May 22nd to 28th: Work will be completed at the intersection of Lorne Avenue and Queen Street.

June 16 → September 01 2022

Lorne Avenue - Road Closure (Eagle Street - Davis Drive)

Lorne Avenue will be closed from Eagle Street to Davis Drive to non-resident traffic as of June 16, 2022 for construction until September 1st, 2022. During this time, only residents and emergency services will be allowed access at all times.

May 02 2022

Phase 2 Commencement (Timothy Street - Davis Drive)

August 03 2021

Phase 1 Commencement (Eagle Street to Timothy Street)

March 16 2021

Virtual Public Information Centre for the Lorne Avenue Reconstruction Project

A Public Information Centre was hosted on March 16, 2021 for residents to learn more about the design and technical aspect of the project. 

February 27 2020

Public Information Centre for Lorne Avenue Reconstruction Project

At this Public Information Centre, residents had the opportunity to view draft plans, inquire about these plans and offer comments. 

April 10 2019

Public Consultation Centre for Public Information Centre for Lorne Avenue Reconstruction Project