Lorne Avenue Road Reconstruction and Traffic-Calming Demonstration (Eagle Street to Davis Drive)

Share on Facebook Share on Twitter Share on Linkedin Email this link

The Lorne Avenue Traffic-Calming Demonstration project incorporates various techniques to lower traffic speeds.

The work on Lorne Avenue will include:

  • Replacement of the watermain and water services to the property line;
  • Replacement of sanitary sewers and sanitary services to the property line;
  • Replacement of storm sewers and catch basins, with implementation of some Low Impact Development (LID) features to help adapt to a changing climate;
  • Road narrowing, speed mitigation measures, automated speed and volume measurement devices, bike lanes and street furniture to provide a “complete street” design; and
  • New Accessibility for Ontarians with Disabilities Act (AODA) compliant sidewalks and associated road features.

Construction work on Lorne Avenue started in August 2021, and the majority of Phase 1, between Eagle and Timothy was completed by December 2021. In 2022, construction crews have been working on completing the remainder of the street w

Construction is currently on schedule, with the majority of construction work, including underground sewers, curb, sidewalks and the first coat of asphalt throughout the project completed for 2022.

As of May 8, 2023, phase 3 of the project will begin which includes final restoration, including the topcoat of the asphalt.

The Town will be regularly providing updates on this website, which are also provided by hand delivery to residents in the construction area. Those notices are summarized below.

A Resident Ambassadors group is meeting with the Construction Team on a bi-weekly basis, and has been in touch with residents to share information by email. To be added to the mailing list, please contact Anthony Riley (ariley@newmarket.ca).

If you have any questions or comments, please email Anthony Riley, Capital Works Project Manager at ariley@newmarket.ca

The Lorne Avenue Traffic-Calming Demonstration project incorporates various techniques to lower traffic speeds.

The work on Lorne Avenue will include:

  • Replacement of the watermain and water services to the property line;
  • Replacement of sanitary sewers and sanitary services to the property line;
  • Replacement of storm sewers and catch basins, with implementation of some Low Impact Development (LID) features to help adapt to a changing climate;
  • Road narrowing, speed mitigation measures, automated speed and volume measurement devices, bike lanes and street furniture to provide a “complete street” design; and
  • New Accessibility for Ontarians with Disabilities Act (AODA) compliant sidewalks and associated road features.

Construction work on Lorne Avenue started in August 2021, and the majority of Phase 1, between Eagle and Timothy was completed by December 2021. In 2022, construction crews have been working on completing the remainder of the street w

Construction is currently on schedule, with the majority of construction work, including underground sewers, curb, sidewalks and the first coat of asphalt throughout the project completed for 2022.

As of May 8, 2023, phase 3 of the project will begin which includes final restoration, including the topcoat of the asphalt.

The Town will be regularly providing updates on this website, which are also provided by hand delivery to residents in the construction area. Those notices are summarized below.

A Resident Ambassadors group is meeting with the Construction Team on a bi-weekly basis, and has been in touch with residents to share information by email. To be added to the mailing list, please contact Anthony Riley (ariley@newmarket.ca).

If you have any questions or comments, please email Anthony Riley, Capital Works Project Manager at ariley@newmarket.ca

  • Lorne Avenue - Construction Corner Update - Week of December 19, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a resident of Lorne Avenue, you have been receiving regular notices from the Town of Newmarket regarding the reconstruction project in your area. Thank you for your continued patience and support on this project.

    The Town’s contractor has completed most of the restoration work within the boulevards, including sidewalks and topsoil placement. The project will shut down for the winter months, and resume with Phase 3, including elevated coloured concrete intersections, final surface asphalt, permanent pavement markings and final restoration in spring of 2023.

    Work completed over the last two weeks:

    • Remaining driveway and walkway restorations were completed;

    • Topsoil and sod were completed to the extent possible;

    • Installation of new signage; and

    • Temporary pavement markings.

    Work anticipated over the next few months:

    • Minor cleanup work and addressing of deficiencies where possible.

    Detour routes for vehicular traffic ended November 30. Local access for residents, pedestrians and emergency vehicles has been maintained throughout the project. Please use caution and drive slowly through the site, be mindful of pedestrians and children trying to navigate their way safely through the site. The detour using Main Street is no longer in use.

    Information on this project is being communicated through this Construction Corner, heynewmarket.ca/lorne and by your Construction Liaison Committee representatives.

    The Town values your feedback on these updates, and appreciates your continued patience while we proceed with this reconstruction project. Please contact us at 905-895-5193 to provide your thoughts.

  • Lorne Avenue - Construction Corner Update - Week of December 5, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a resident of Lorne Avenue, you have been receiving regular notices from the Town of Newmarket regarding the reconstruction project in your area. Thank you for your continued patience and support on this project.

    The Town’s contractor continues to make progress in completing the project, and is currently focused on completing restoration work within the boulevards, including sidewalks and topsoil placement prior to winter. Weather has been fairly cooperative but concrete supply remains an issue. While Phase 2 works are expected to be completed prior to the holidays, the contractor will be returning in the spring for Phase 3, which includes elevated coloured concrete intersections, surface asphalt, final pavement markings, and final restoration of all areas.

    Work completed over the last two weeks:

    • Curbs are complete, with the exception of small sections behind catch basins;

    • Base asphalt has been installed throughout the project area;

    • Topsoil and sod have been partially installed for approximately 70 per cent of the project;

    • Driveway restorations have been partially completed, with driveways north of Millard Avenue still outstanding; and

    • The majority of sidewalk has been installed, with minor deficiencies remaining.

    Work anticipated over the next few weeks:

    • Remaining driveway and walkway restorations will be completed;

    • Topsoil and sod will be completed to the extent possible. Sod is weather dependent as it may not be harvested any longer due to winter conditions.

    • Installation of new signage; and

    • Remaining temporary pavement markings.

    During the remaining construction, the contractor will endeavour to maintain access to driveways wherever possible. At times, such as when sidewalk is being poured and allowed to cure, this may not be possible. Residents will be notified prior to driveway access disruption, and parking on side streets may be required. The disruption notice should be placed on dashboards to avoid ticketing during overnight parking.

    Detour routes for vehicular traffic ended November 30. Local access for residents, pedestrians and emergency vehicles is maintained. Please use caution and drive slowly through the construction site as construction continues. Kindly be mindful of workers, construction vehicles, pedestrians and children trying to negotiate their way safely through the site. The detour using Main Street will no longer be in effect.

    Information on this project is being communicated through this Construction Corner, heynewmarket.ca/lorne and by your Construction Liaison Committee representatives.

    The Town values your feedback on these updates and appreciates your continued patience while we proceed with this reconstruction project. Please contact us at 905-895-5193 to provide your thoughts.

  • Lorne Avenue - Construction Corner Update - Week of November 21, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a resident of Lorne Avenue, you have been receiving regular notices from the Town of Newmarket regarding the reconstruction project in your area. Thank you for your continued patience and support on this project.

    The Town’s contractor continues to make progress in completing the project, and is currently focused on completing restoration work within the boulevards, including sidewalks and topsoil placement prior to winter.

    Over the past two weeks:

    • Curb installation has been completed;

    • Sidewalk installation was completed south of the Millard Avenue intersection;

    • Base asphalt has been installed from Timothy Street to Davis Drive; and,

    • Restoration works, driveway restoration and boulevard re-grading are ongoing.

    Over the next two weeks:

    • Sidewalk installation north of Millard Avenue will be completed; and,

    • Restoration works will continue, including the removal of existing abandoned fire hydrants, placement of topsoil within the boulevards and installation of concrete Canada Post superbox pads.

    While issues associated with a shortage of available construction materials have slowed progress on the project, works associated with Phase 2 of the project remain on schedule to be completed by year end. Final restoration, including raised intersections and top asphalt, will be resumed in the spring and will be completed in 2023.

    During sidewalk construction, the contractor will endeavour to maintain access to driveways wherever possible. At times, such as when sidewalk is being excavated, formed and poured, this may not be possible. Residents will be notified prior to driveway access disruption, and parking on side streets may be required. The disruption notice should be placed on dashboards to avoid ticketing during overnight parking.

    Detour routes for vehicular traffic will remain in place until the end of November. Local access for residents, pedestrians and emergency vehicles will be maintained. Signage is in place to ensure safe traffic flow. Please use caution and drive slowly through the construction site as construction continues.

    Kindly be mindful of workers, construction vehicles, pedestrians and children trying to negotiate their way safely through the site and use detours whenever possible.

    Waste and recycling curbside pick-up by Green for Life (GFL) will not be disrupted during construction.

    Any changes to the pick-up schedule will be communicated to residents in advance. Information on this project is being communicated through this Construction Corner, through heynewmarket.ca/lorne and by your Construction Liaison Committee representatives.

    The Town values your feedback on these updates and appreciates your continued patience while we proceed with this reconstruction project. Please contact us at 905-895-5193 to provide your thoughts.

  • Lorne Avenue - Construction Corner Update - Week of November 7, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a resident of Lorne Avenue, you have been receiving regular notices from the Town regarding the reconstruction project in your area. Thank you for your continued patience and support with the project.

    The contractor and sub-contractors continue with road reconstruction between Timothy Street and Davis Drive, and restoration of the right-of-way throughout the project. Currently, the focus is on getting all curbs and sidewalks completed, followed by installation of asphalt on the road. In parallel, restoration works within the boulevard continues.

    Over the past two weeks:

    • Curb installation has continued, with most curbs now installed;

    • Sidewalk installation has continued;

    • Fine grading and compaction of the road base has continued; and

    • Restoration works, including retaining walls, driveway restoration and boulevard re-grading continue.

    Over the next two weeks:

    • Remaining curbs will be completed throughout the project area;

    • Both sides of the sidewalk north of Millard Avenue will be poured;

    • Fine grading and compaction of the road will be completed; and

    • Restoration works will continue.

    Installation of the base coat of asphalt is tentatively scheduled for the middle of November. While works remain on schedule to be completed by year end, issues associated with a shortage of available construction materials have slowed works on the project.

    The major works in Phase Two of this project are expected to be completed by end of 2022, with restoration and Phase Three work resuming in the spring of 2023.

    During road building, the contractor will try maintain access to driveways wherever possible. At times, such as when sidewalk is being constructed, this may not be possible. Residents will be notified prior to driveway access disruption, and parking on side streets may be required. Place this notice on dashboards to avoid ticketing during overnight parking.

    Please note: Rolling temporary road closures will be necessary in the area to allow for the completion of this project. Detour routes for vehicular traffic will remain in place until the project is completed. Local access for residents, pedestrians and emergency vehicles will be maintained. Signage is in place to ensure safe traffic flow. Please note that road conditions may deteriorate during construction, especially when it rains.

    Although crews do their best to maintain the road in good condition for vehicles, there will be bumps and holes to contend with. Please use caution and drive slowly to maintain control of your vehicle and to avoid any potential damage and use detours whenever possible.

    Waste and recycling curbside pick-up by Green for Life (GFL) will not be disrupted. Any changes to the pick-up schedule will be communicated to residents in advance. Information on this project will be posted at www.heynewmarket.ca/lorne and by your Construction Liaison Committee representatives.

    The Town values your feedback. Contact us at 905-895-5193 to provide your thoughts.

  • Lorne Avenue - Construction Corner Update - Week of October 24, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a resident of Lorne Avenue, you have been receiving regular notices from the Town of Newmarket regarding the reconstruction project in your area. Thank you for your continued patience and support with the project.

    The contractor and sub-contractors continue with road reconstruction between Timothy Street and Davis Drive, and restoration of the right-of-way throughout the project. Currently, the focus is on getting all concrete work completed, beginning with curbs, followed by sidewalk construction. In parallel, new retaining walls and restoration works between private properties and the sidewalk are being installed where required.

    Over the past two weeks:

    • Excavation of the existing road materials was completed;

    • Installation of retaining walls north of Timothy Street on the east side of Lorne Avenue was initiated; and,

    • The sidewalks on the east side of Lorne Avenue from Millard Avenue to Timothy Street were completed.

    Over the next two weeks:

    • Remaining curbs and gutters will be completed throughout the project area;

    • Boulevard restoration, including re-grading, driveway restoration, and retaining walls will continue;

    • Fine grading of the road will be initiated in preparation of asphalt paving; and,

    • The mailbox pad at Lorne Avenue and Park Avenue will be poured.

    Installation of the base coat of asphalt is tentatively scheduled for the middle of November. While works remain on schedule to be completed by year end, issues associated with a shortage of available concrete have slowed works on the project. The major works in Phase Two of this project are expected to be completed by end of 2022, with restoration work resuming in the spring of 2023.

    During road building, the contractor will endeavour to maintain access to driveways wherever possible. At times, such as when curb and sidewalk are being constructed, this may not be possible. Residents will be notified prior to driveway access disruption, and parking on side streets may be required. The disruption notice should be placed on dashboards to avoid ticketing during overnight parking.

    Please note: Rolling temporary road closures will be necessary in the area to allow for the completion of this project.

    Detour routes for vehicular traffic will remain in place until the project is completed. Local access for residents, pedestrians and emergency vehicles will be maintained. Signage is in place to ensure safe traffic flow. Please note that road conditions may deteriorate during construction, especially when it rains. Although crews do their best to maintain the road in good condition for vehicles, there will be bumps and holes to contend with. Please use caution and drive slowly to maintain control of your vehicle and to avoid any potential damage, and use detours whenever possible.

    Waste and recycling curbside pick-up by Green for Life (GFL) will not be disrupted during construction. Any changes to the pick-up schedule will be communicated to residents in advance.

    Information on this project is being communicated through this Construction Corner, www.heynewmarket.ca/lorne and by your Construction Liaison Committee representatives.

    The Town values your feedback on these updates and appreciates your continued patience while we proceed with this reconstruction project. Please contact us at 905-895-5193 to provide your thoughts.

  • Lorne Avenue - Construction Corner Update - Week of October 3, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a resident of Lorne Avenue, you have been receiving regular notices from the Town of Newmarket regarding the reconstruction project in your area. Thank you for your continued patience and support with the project.

    The contractor has recently completed underground works on the project, and has now shifted focus to the reconstruction of the road. This involves the excavation of the materials currently present and replacement of a new road base, followed by concrete curb and sidewalk construction, and then asphalt placement.

    There are two operations currently being completed in parallel by the contractor:

    - Concrete work between Timothy Street and Millard Avenue

    - Road building between Millard Avenue and Davis Drive

    While works remain on schedule to be completed by year end, issues associated with a shortage of available concrete have slowed works between Timothy Street and Millard Avenue, and may delay progress in the area north of Millard Avenue once concrete construction works are initiated.

    Over the past two weeks:

    • The sidewalk on the west side of Lorne Avenue from Timothy Street to Millard Avenue was installed;

    • Roadway catch basins and other stormwater accessories north of the Millard Avenue intersection were completed;

    • The sidewalk on the east side of Lorne Avenue, south of Millard Avenue was initiated; and,

    • Restoration work, including retaining walls, within the Phase One area south of Timothy Street was completed.

    Over the next two weeks:

    • Excavation of the existing road materials and placement of new granular material will continue north of Millard Avenue; and,

    • The contractor will pour the sidewalks on the east side of Lorne Avenue from Millard Avenue to Timothy Street.

    Waste and recycling curbside pick-up by Green for Life (GFL) will not be disrupted during construction. Any changes to the pick-up schedule will be communicated to residents in advance.

    During road building, the contractor will endeavour to maintain access to driveways wherever possible. At times, such as when deeper excavations are required, this may not be possible. Residents will be notified prior to driveway access disruption, and parking on side streets may be required. The disruption notice should be placed on dashboards to avoid ticketing during overnight parking.

    Please note: Rolling temporary road closures will be necessary in the area to allow for the completion of this project.

    Detour routes for vehicular traffic will remain in place until the project is completed. Local access for residents, pedestrians and emergency vehicles will be maintained. Signage is in place to ensure safe traffic flow. Please note that road conditions may deteriorate during construction, especially when it rains. Although crews do their best to maintain the road in good condition for vehicles, there will be bumps and holes to contend with. Please use caution and drive slowly to maintain control of your vehicle and to avoid any potential damage, and use detours whenever possible. The major works in Phase Two of this project are expected to be completed by end of 2022, with restoration work resuming in the spring of 2023.

    Information on this project is being communicated through this Construction Corner, www.heynewmarket.ca/lorne and by your Construction Liaison Committee representatives.

    The Town values your feedback on these updates and appreciates your continued patience while we proceed with this reconstruction project. Please contact us at 905-895-5193 to provide your thoughts.

  • Lorne Avenue - Construction Corner Update - Week of September 12, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a resident of Lorne Avenue, you have been receiving regular notices from the Town of Newmarket regarding the reconstruction project in your area. Thank you for your continued patience and support.

    Underground works on the project are nearing completion, with only stormwater works accessories remaining. As soon as these underground works are completed, the project will shift into full restoration mode, with the completion of all roads, sidewalks, and associated surface works.

    Over the past two weeks:

    • All watermain connections were completed;

    • All sanitary sewers including resident services were completed;

    • Curb installation between Timothy Street and Millard Avenue has been initiated;

    • The Queen Street Traffic Island was completed.

    Over the next two weeks:

    • The sidewalk on the west side of Lorne Avenue from Timothy Street to Millard Avenue will be installed;

    • Roadway catch basins and other stormwater accessories north of the Millard Avenue intersection will be completed;

    • Excavation of the existing road materials north of Millard Avenue will be initiated, with new granular material being imported to form the new base for the road;

    • Road building will continue north of Millard Avenue in a northerly direction;

    • Residents are expected to see various restoration work starting at Eagle Street and progressing north, which will include installation of some retaining walls.

    Waste and recycling curbside pick-up by Green for Life (GFL) will not be disrupted during construction. Any changes to the pick-up schedule will be communicated to residents in advance.

    During road building, the contractor will endeavour to maintain access to driveways wherever possible. At times, such as when deeper excavations are required, this may not be possible. Residents will be notified prior to driveway access disruption, and parking on side streets may be required. The disruption notice should be placed on dashboards to avoid ticketing during overnight parking.

    Please note: Rolling temporary road closures will be necessary in the area to allow for the completion of this project.

    Detour routes for vehicular traffic will remain in place until the project is completed. Local access for residents, pedestrians and emergency vehicles will be maintained. Signage is in place to ensure safe traffic flow. Please note that road conditions may deteriorate during construction, especially when it rains. Although crews do their best to maintain the road in good condition for vehicles, there will be bumps and holes to contend with. Please use caution and drive slowly to maintain control of your vehicle and to avoid any potential damage, and use detours whenever possible.

    The major works in Phase Two of this project are expected to be completed by December of 2022, with restoration work resuming in the spring of 2023, if necessary.

    Information on this project is being communicated through this Construction Corner, www.heynewmarket.ca/lorne and by your Construction Liaison Committee representatives.

    The Town values your feedback on these updates and appreciates your continued patience while we proceed with this reconstruction project. Please contact us at 905-895-5193 to provide your thoughts.

  • Notice of Temporary Water Disruption

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Dear Resident,


    Please note that water service to your residence will be shut off from 8:00 pm to 5:00 am

    on the following date:


    Tuesday, September 6th, 2022


    The above noted water service interruption will facilitate the new watermain connections

    to 25 & 26 Lorne Ave.


    Thank you for your cooperation.


    Should you have any concerns, please speak to the foreman on site or contact Mr. Sean

    Konopud, Site Inspector, Ainley Group, during regular business hours (8am to 6pm) at

    416-558-0157.


    For after-hour emergencies please contact the Town’s 24-hour dispatch at

    (905) 895-5193.

  • Lorne Avenue - Construction Corner Update - Week of August 29th, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a resident of Lorne Avenue, you have been receiving regular notices from the Town of Newmarket regarding the reconstruction project in your area. Thank you for your continued patience and support.

    Currently, the Contractor is continuing with road works between Timothy Street and Millard Avenue. North of Millard Avenue, the Contractor is finalizing the service connections between the new watermain and individual homes. The Contractor is also currently finalizing works with the island extension on Queen Street, just west of Lorne Avenue.

    The kids are going back to school next week, and the Town is actively working with the project team to make the street as accessible as possible. There will be one sidewalk open at all times, and access will be provided to all residents. We ask that if any issues are noted before and after school drop off, to please let the project team know and they will be addressed immediately.

    Over the past two weeks:

    • All sanitary sewer work was completed;

    • Mainline storm sewer work was completed;

    • Watermain was installed from Millard Avenue to Davis Drive, and tested to ensure water quality and pressure standards have been met;

    • Road excavation and granular base is underway from Timothy Street to Millard Avenue; and,

    • Concrete works and signage on the Queen Street Pedestrian Island Extension was completed.

    Over the next two weeks:

    • Concrete curb, gutter and sidewalks will be poured from Timothy Street to Millard Avenue;

    • Watermain connections are to be completed north of Millard Avenue; and,

    • Further cleanup of the area to improve conditions for back to school will be completed.

    Phase two of this project is expected to be completed by December of 2022.

    Please note: Rolling road closures are necessary in the area to allow for the completion of this project.

    Waste and recycling curbside pick-up by Green for Life (GFL) will not be disrupted during construction. If there are any issues with garbage pickup, please contact the Town’s project manager to organize alternate pickup.

    Detour routes for bicycles and vehicular traffic will remain in place until the project is completed. Local access for residents, pedestrians and emergency vehicles will be maintained. Signage is in place to ensure safe traffic flow.

    Information on this project is being communicated through this Construction Corner, by your Construction Liaison Committee representatives and through the Town’s Hey Newmarket website.

    The Town values your feedback on these updates and appreciates your continued patience while we proceed with this project. Please contact us at 905-895-5193 to provide your thoughts.


  • Lorne Avenue - Construction Corner Update - Week of August 15th, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a resident of Lorne Avenue, you have been receiving regular notices from the Town of Newmarket regarding the reconstruction project in your area. Once again, we would like to thank you for your patience and support throughout this time.

    Currently, the Contractor is completing road works, including the road base, curb and sidewalks, between Timothy Street and Millard Avenue. Construction of the underground sewer and watermain between Davis Drive and Millard Avenue is now complete. Once testing of the new watermain is finalized, the connections between each property and the new watermain will be installed, and each home will be transferred over to the new system. Phase 2 of the Lorne Avenue project, which extends to Davis Drive, is expected to be completed in December of 2022.

    Over the past two weeks:

    • Storm sewer and watermain reconstruction was completed on Lorne Avenue from Millard Avenue to the Davis Drive intersection;

    • Watermain testing has been completed; and,

    • Road building between Park Avenue and Timothy Street has commenced.

    Over the next two weeks:

    • Road building between Park Avenue and Timothy Street will continue;

    • Road building between Park Avenue and Millard Avenue will commence; and,

    • Watermain service connections will begin north of Millard Avenue.

    Waste and recycling curbside pick-up by Green for Life (GFL) will not be disrupted during construction. Any changes to the pick-up schedule will be communicated to residents in advance. Should there be any issues with garbage collection, please contact the Town or Town’s representatives, and we will contact GFL to make pick-up arrangements.

    Please note: Rolling temporary road closures will be necessary in the area to allow for the completion of this project.

    Detour routes for through vehicular traffic will remain in place until the project is completed. Local access for residents, pedestrians and emergency vehicles will be maintained. Signage is in place to ensure safe traffic flow.

    Waste and recycling curbside pick-up by Green for Life (GFL) will not be disrupted during construction. Any changes to the pick-up schedule will be communicated to the residents in advance.

    Information on this project is being communicated through this Construction Corner, through the Town’s information website and by your Construction Liaison Committee representatives.

    The Town values your feedback on these updates and we appreciate your patience while we proceed with this reconstruction project. Please contact us at 905-895-5193 to provide your thoughts.

Page last updated: 04 May 2023, 03:23 PM