Watermain Lining Project: Notice 5
Dear Resident,
This notice provides an update on the Newmarket Heights Watermain Lining Project and the upcoming works within the culde-
sac of Willow Lane (see map on the reverse side of this notice).
As part of the project, the Town will install a new watermain auto-flusher to enhance water circulation within the water
system. To facilitate this installation, a new catch basin, manhole, and a small new water pipe will be installed, connecting
the existing watermain on Willow Lane to the new auto-flusher (see reverse side of this notice for the approximate
locations).
To install these new features, a trench will be excavated within the roadway and boulevard, causing intermittent traffic
delays and temporary disruptions to driveway access for approximately one week. The contractor plans to start this work
during the week of October 2nd, barring any unforeseen circumstances. The contractor will notify you before the work begins
and provide information about parking impacts. At times you may be asked to park on Willow Lane, north of Longford to
facilitate this work. If you have planned deliveries, events, or accessibility concerns, please contact the undersigned to
coordinate. After the installation of the auto-flusher and related features, the contractor will remove and replace deficient
sections of curb and will proceed to resurface the entire cul-de-sac with new asphalt.
Waste collection will continue as usual, and we remind all residents to place garbage, recycle bins, and green bins out by
7:00a.m.
As with all construction projects, residents may experience dust, noise, and minor vibrations. The Town and contractor will
minimize these inconveniences as much as possible.
Should you have any questions regarding the project prior to or during the work, please contact Eric Engman, Capital
Works Project Manager at the Town of Newmarket, by emailing eengman@newmarket.ca or by calling 905-895-5193 ext.
2519.