Share Penn Ave and 56 Charles St Sanitary Sewer Upsizing Project [Completed] on FacebookShare Penn Ave and 56 Charles St Sanitary Sewer Upsizing Project [Completed] on TwitterShare Penn Ave and 56 Charles St Sanitary Sewer Upsizing Project [Completed] on LinkedinEmail Penn Ave and 56 Charles St Sanitary Sewer Upsizing Project [Completed] link
Consultation has concluded
About the Project
The Town of Newmarket is working with its Engineering Consultant, Ainley Group on sanitary sewer replacement projects located along 56 Charles Street and Penn Avenue, between Lindsay Avenue and Hill Street.
The proposed works include the removal of the existing sanitary sewer and replacement with a larger
sized sewer. This sewer upsizing project has been identified in the Town of Newmarket’s Water Waste
Water Master Plan as required to meet future sanitary sewer capacity as Newmarket continues to grow
The Town of Newmarket is working with its Engineering Consultant, Ainley Group on sanitary sewer replacement projects located along 56 Charles Street and Penn Avenue, between Lindsay Avenue and Hill Street.
The proposed works include the removal of the existing sanitary sewer and replacement with a larger
sized sewer. This sewer upsizing project has been identified in the Town of Newmarket’s Water Waste
Water Master Plan as required to meet future sanitary sewer capacity as Newmarket continues to grow
Penn Ave and 56 Charles St Sanitary Sewer Upsizing Project [Completed] has finished this stage
A public information centre was hosted on May 17, 2022. At the meeting the Town's Consultant, Ainley Group, notified the public of the construction, walked through the final drawings and discussed the scope of the project along with expected disruptions. View a copy of the presentation under the 'Important Documents' section.
Charles St Construction Start - June 2022
Penn Ave and 56 Charles St Sanitary Sewer Upsizing Project [Completed] has finished this stage
Penn Ave Construction Start - June 22, 2022
Penn Ave and 56 Charles St Sanitary Sewer Upsizing Project [Completed] has finished this stage
Public Works Services, Operations Centre
ROAD CLOSURE NOTIFICATION - CONSTRUCTION
Report status: Preliminary
Incident Detail
Level
High
Description
Road Closure
Sanitary Sewer Main Line replacement under Capital works project.
Work being performed by GFL Infrastructure
Initiated By:
Town of Newmarket, Engineering Services
Impact to Customers
Full Road Closure daily Mon. to Fri.
Location
Penn Ave., Newmarket, ON between Lindsay Avenue and Hill St
Date (Start)
June 22, 2022
Time
7:00 am to 7:00 pm – Daily
Detour
See below
Resolution
[Date and Time]
Date: July 8, 2022
Time: 7:00 pm
Summary: Road to be re-opened
Contact(s):
Mark Gregory Manager, Operations Public Works Services