Notice 2 - January 31, 2023

This notice is to provide an update on the tentative timelines for the Queen Street Bridge Rehabilitation Project that was first communicated to you on November 25, 2022 . As part of the first phase of the project, Bell Canada will be conducting utility work along Queen Street in preparation for the bridge rehabilitation work. (Please see the map on the reverse side for more information on the project area).

Bell advised the Town that the utility work start date has been delayed and below is the updated tentative schedule:

Phase 1: Bell Canada utility work

  • Directional drilling of telecommunication conduit under the tracks (March 2023 – May 2023)
  • Splicing and reconfiguration of telecommunication cables (May 2023 – Summer 2024)

Phase 2: Town of Newmarket infrastructure work to Queen Bridge

  • Replacement of the Queen Street Bridge structure (Summer 2024 subject to completion of utility work)

The first notice and other updates regarding the project can be accessed by visiting heynewmarket.ca/QueenBridge.

In order for Bell’s contractor (Avertex) to relocate their telecommunication wires, lane closures, traffic detours, and road restrictions will be required from March 2023 to May 2023, depending on the tendering process, obtaining permits and suitable weather for the construction.

Exact details of Bell’s schedule for required lane closures, detours, and road restrictions will be provided to you in a future notice prior to Bell starting their work. Once these details are provided to the Town by Bell Canada, the Town will contact local businesses and residents who will be directly impacted by the work to review the proposed construction methodology, planned detour routes if needed, and possible impacts.

Residents will be provided hand-delivered notices for timely and urgent updates about the project. You are also encouraged to visit our website for more frequent updates regarding the project at: heynewmarket.ca/QueenBridge

As with all construction works, residents may experience dust, noise and minor vibration. The Town, Bell, and Avertex will limit these inconveniences as much as possible and will keep a close eye to ensure that they do not exceed acceptable limits.

Should you have any questions regarding the project prior to or during the work, please reach out to Eric Engman, Capital Works Project Manager at the Town of Newmarket by emailing eengman@newmarket.ca or by calling 905-895-5193 ext. 2519. We thank you for your patience and understanding during this work.