Eagle Street Resurfacing

Eagle Street Resurfacing

The Town of Newmarket is pleased to advise that Eagle Street Resurfacing is scheduled to begin on November 19th, with work anticipated to be completed by December 2026. The Town’s contractor, Forest Paving, has commenced preparation work for resurfacing, with on-site inspection provided by Gannet Flemming (GFT).

Scope of Work

  • Remove and replacement of deficient sidewalk bays
  • Remove and replacement of deficient curb and gutter
  • Adjustments of manholes, catch basins and water valves.
  • Grinding of asphalt scheduled for November 19th
  • Paving of surface asphalt scheduled for November 23rd

What to Expect During Construction

  • Typical work hours will be from Monday to Friday between 7 a.m. – 7 p.m.
  • Weekend and/ or nightwork may be required
  • Noise, dust, and minor vibration
  • Garbage and recycling collection will continue
  • Temporary driveway and service restrictions with advanced notice
  • The road will be limited to local-traffic only
  • Access to business will remain open at all times
  • York Region transit busses, garbage pick-up and emergency access will be maintained throughout construction.

Grinding and paving remains dependent on weather. The Town intends to complete the paving works in 2026, however, should weather conditions become unfavorable, the Town will defer paving until spring 2027.

Project Benefits

This work will improve the condition of the road surface and extend its life. New pavement, sidewalk repairs, and curb upgrades will create a smoother, safer, and more accessible experience for road users.

We appreciate your patience during this important upgrade.