Road Resurfacing Projects

Share Road Resurfacing Projects on Facebook Share Road Resurfacing Projects on Twitter Share Road Resurfacing Projects on Linkedin Email Road Resurfacing Projects link

2025/2026 Road Resurfacing Projects

The Town of Newmarket will be undertaking multiple road resurfacing projects in 2025 and 2026. These projects will include grinding and resurfacing of the roadway, line painting, catch basin repairs, curb and sidewalk repairs and accessibility improvements.

For 2025 the Town is conducting Road Resurfacing on the following roads:

  • Clearmeadow Blvd from Yonge to Bathurst (July to September)
  • Savage Road from Yonge to Yonge (July to September)
  • Gorham Street from Leslie to Harry Walker Parkway (August to October)

Construction is anticipated to begin in the summer months, with traffic access to homes and businesses maintained throughout the duration of the work. Advance notice will be provided to residents regarding timelines and any potential disruptions to driveway access.

Please see below for the project locations and refer to the Project Updates section on the right-hand side of this page for the latest information.



Clearmeadow Boulevard - July 2025 to September 2025

Newmarket will be undertaking a road resurfacing project on Clearmeadow Boulevard, from Bathurst Street to Yonge Street. This resurfacing project aims to improve the condition of the road and sidewalk and enhance community safety.

The project includes the removal and replacement of existing asphalt, and minor repairs to the curb, sidewalk and other infrastructure within the road allowance on Clearmeadow Boulevard.

Project Update - Clearmeadow Boulevard (Week of July 28th, 2025)

  • Road grinding has been completed.

  • Manhole adjustments have been completed.

  • Base asphalt repairs are scheduled for this week.

  • Road resurfacing is anticipated to begin later this week (week of July 28) or early next week (week of August 4), weather permitting.

See all project updates on Clearmeadow Boulevard Road Resurfacing Project.



Savage Road - July 2025 to September 2025

See all project updates on Savage Road Road Resurfacing Project.



Gorham Street - August 2025 to October 2025

Work on Gorham Street is anticipated to begin in August 2025. Please check back for updates.



2026 Resurfacing Projects:

Columbus Way - May 2026


Sawmill Valley Drive - May 2026


Sandford Street - July 2026




2025/2026 Road Resurfacing Projects

The Town of Newmarket will be undertaking multiple road resurfacing projects in 2025 and 2026. These projects will include grinding and resurfacing of the roadway, line painting, catch basin repairs, curb and sidewalk repairs and accessibility improvements.

For 2025 the Town is conducting Road Resurfacing on the following roads:

  • Clearmeadow Blvd from Yonge to Bathurst (July to September)
  • Savage Road from Yonge to Yonge (July to September)
  • Gorham Street from Leslie to Harry Walker Parkway (August to October)

Construction is anticipated to begin in the summer months, with traffic access to homes and businesses maintained throughout the duration of the work. Advance notice will be provided to residents regarding timelines and any potential disruptions to driveway access.

Please see below for the project locations and refer to the Project Updates section on the right-hand side of this page for the latest information.



Clearmeadow Boulevard - July 2025 to September 2025

Newmarket will be undertaking a road resurfacing project on Clearmeadow Boulevard, from Bathurst Street to Yonge Street. This resurfacing project aims to improve the condition of the road and sidewalk and enhance community safety.

The project includes the removal and replacement of existing asphalt, and minor repairs to the curb, sidewalk and other infrastructure within the road allowance on Clearmeadow Boulevard.

Project Update - Clearmeadow Boulevard (Week of July 28th, 2025)

  • Road grinding has been completed.

  • Manhole adjustments have been completed.

  • Base asphalt repairs are scheduled for this week.

  • Road resurfacing is anticipated to begin later this week (week of July 28) or early next week (week of August 4), weather permitting.

See all project updates on Clearmeadow Boulevard Road Resurfacing Project.



Savage Road - July 2025 to September 2025

See all project updates on Savage Road Road Resurfacing Project.



Gorham Street - August 2025 to October 2025

Work on Gorham Street is anticipated to begin in August 2025. Please check back for updates.



2026 Resurfacing Projects:

Columbus Way - May 2026


Sawmill Valley Drive - May 2026


Sandford Street - July 2026




  • Project Update: Clearmeadow Boulevard

    Share Project Update: Clearmeadow Boulevard on Facebook Share Project Update: Clearmeadow Boulevard on Twitter Share Project Update: Clearmeadow Boulevard on Linkedin Email Project Update: Clearmeadow Boulevard link

    Project Update #9- Clearmeadow Boulevard (Week of July 28th 2025)

    • Road grinding has been completed
    • Manhole adjustments have been completed
    • Base Asphalt repairs are scheduled for this week
    • Road Resurfacing is anticipated to begin later this week (Week of July 28th) or early next week (Week of August 4th), weather permitting


    Project Update #8- Clearmeadow Boulevard (Week of July 21st 2025)

    • Road grinding has begun in preparation for resurfacing work
    • After grinding work, manhole adjustments will take place
    • Resurfacing is expected to take place in in the following week (week of July 28th), weather permitting


    Project Update #7- Clearmeadow Boulevard (Week of December 2nd)

    • Due to unfavorable temperatures for paving, road resurfacing is postponed until summer 2025.
    • Driveway and boulevard restorations ongoing. To be completed by Early December (likely late this week or early next week)
    • A review of the resorted areas will be done in Spring 2025, and any areas that are not completed to the Towns satisfaction will be replaced.


    Project Update #6- Clearmeadow Boulevard (Week of November 25th)

    • Curb removal and replacements are complete.
    • Driveway and Sod restorations ongoing. To be completed by Early December.
    • Due to unfavorable temperatures for paving, road resurfacing is likely to be postponed until spring 2025. However, if an unseasonably warm day occurs in December, paving may proceed at that time. As it stands, the work is tentatively scheduled for spring 2025.


    Project Update #5- Clearmeadow Boulevard (Week of November 18th)

    • Curb removal and replacements are ongoing throughout Clearmeadow. Anticipated to be completed this week.
    • Driveway restorations and placement of topsoil and sod will commence in the next week or two.
    • Road paving is tentatively scheduled for the next 2 weeks- weather permitting. Should weather not allow for paving this year, then paving will be deferred to Spring 2025.


    Project Update #4 - Clearmeadow Boulevard (Week of November 11th)

    • Curb removal and replacements have begun throughout Clearmeadow.
    • Sidewalk removals and replacements are still underway along south side of Clearmeadow. The majority of the north side sidewalk work has been completed.
    • After completion of curb and sidewalk work, road grinding and manhole adjustments will begin- anticipated to start in 1-2 weeks, weather permitting.


    Project Update #3 - Clearmeadow Boulevard (Week of November 4th)

    • Crews have began sidewalk removal and replacements along the north side of Clearmeadow. Once complete, they will move to the south side of Clearmeadow and begin sidewalk removal and replacements on the south side.
    • After sidewalk removal and replacements are completed on the north and south sides of Clearmeadow, curb removals will begin.


    Project Update #2 - Clearmeadow Boulevard (Week of October 28th)

    • Crews will begin work on Clearmeadow this week, below is a summary of the upcoming work:
    • Curb Replacement: Concrete crews will be mobilizing on-site this week to begin curb replacement work along Clearmeadow Boulevard. You may see crews saw-cutting and removing sections of curb throughout the area. This is expected to take approximately 2–3 weeks to complete.
    • Road Grinding and Manhole Adjustments: Once curb replacements are complete, the contractor will proceed with grinding the road surface and adjusting manholes to prepare for paving.
    • Sidewalk Replacements: Weather permitting, sidewalk replacements may also take place this year. If weather conditions do not allow, this work will be postponed until next year. We will keep you informed with additional updates on the timing for sidewalk replacements


    Project Update #1 - Clearmeadow Boulevard

    • Please be advised that the start of Clearmeadow Boulevard Resurfacing has been slightly delayed and the project is now expected to begin in late October. We appreciate your understanding and will provide further updates as needed.
  • Project Update - Savage Road

    Share Project Update - Savage Road on Facebook Share Project Update - Savage Road on Twitter Share Project Update - Savage Road on Linkedin Email Project Update - Savage Road link

    Project Update #3 - July 29th 2025

    Recent work completed:

    • Majority of sidewalk work has been completed along the south side of Savage Road.

    • Boulevard areas where sidewalk have been replaced have been backfilled with topsoil in preparation of sod.

    What to expect over the next 2 weeks:

    • Continued removal and replacement of sidewalks along the north side.

    • Start of curb removals at residential and commercial driveways, following the sidewalk work.


    Project Update #2 - July 18th 2025

    Construction on Savage Road is underway. Recent work completed:

    • Saw cutting of existing curbs and sidewalks to prepare for removal and replacement.

    • Sidewalk removals have begun along the south side of Savage Road.

    • Curb removals and replacements are underway, starting mainly at intersections to maintain accessibility.

    What to expect over the next 2 weeks:

    • Continued removal and replacement of sidewalks.

    • Construction equipment and crews will remain active in the area; please use caution and follow posted signage.

    • Temporary pedestrian detours may be in place while work is ongoing.


    Project Update #1 - July 11th 2025

    Construction on Savage Road is scheduled to begin in July 2025. Over the next few weeks, residents will notice the placement of construction barrels and traffic control signage along the roadway.

    What to expect in the coming weeks:

    • Saw cutting of curbs and sidewalks will begin shortly after initial setup in preparation for removal.

    • Pedestrian access will be maintained on at least one side of the road at all times.

    • Short term disruptions to driveway access may occur during curb and sidewalk work. Notice will be provided to residents in advance.

    • Emergency access will be maintained at all times.

  • Project Update - Gorham Street

    Share Project Update - Gorham Street on Facebook Share Project Update - Gorham Street on Twitter Share Project Update - Gorham Street on Linkedin Email Project Update - Gorham Street link

    Work on Gorham is anticipated to begin August 2025.