Project Update - Savage Road

Project Update #3 - July 29th 2025

Recent work completed:

  • Majority of sidewalk work has been completed along the south side of Savage Road.

  • Boulevard areas where sidewalk have been replaced have been backfilled with topsoil in preparation of sod.

What to expect over the next 2 weeks:

  • Continued removal and replacement of sidewalks along the north side.

  • Start of curb removals at residential and commercial driveways, following the sidewalk work.


Project Update #2 - July 18th 2025

Construction on Savage Road is underway. Recent work completed:

  • Saw cutting of existing curbs and sidewalks to prepare for removal and replacement.

  • Sidewalk removals have begun along the south side of Savage Road.

  • Curb removals and replacements are underway, starting mainly at intersections to maintain accessibility.

What to expect over the next 2 weeks:

  • Continued removal and replacement of sidewalks.

  • Construction equipment and crews will remain active in the area; please use caution and follow posted signage.

  • Temporary pedestrian detours may be in place while work is ongoing.


Project Update #1 - July 11th 2025

Construction on Savage Road is scheduled to begin in July 2025. Over the next few weeks, residents will notice the placement of construction barrels and traffic control signage along the roadway.

What to expect in the coming weeks:

  • Saw cutting of curbs and sidewalks will begin shortly after initial setup in preparation for removal.

  • Pedestrian access will be maintained on at least one side of the road at all times.

  • Short term disruptions to driveway access may occur during curb and sidewalk work. Notice will be provided to residents in advance.

  • Emergency access will be maintained at all times.

Share Project Update - Savage Road on Facebook Share Project Update - Savage Road on Twitter Share Project Update - Savage Road on Linkedin Email Project Update - Savage Road link
#<Object:0x0000000046ad3d60>