Project Update: Clearmeadow Boulevard

Project Update #7- Clearmeadow Boulevard (Week of December 2nd)

  • Due to unfavorable temperatures for paving, road resurfacing is postponed until spring 2025.
  • Driveway and boulevard restorations ongoing. To be completed by Early December (likely late this week or early next week)
  • A review of the resorted areas will be done in Spring 2025, and any areas that are not completed to the Towns satisfaction will be replaced.


Project Update #6- Clearmeadow Boulevard (Week of November 25th)

  • Curb removal and replacements are complete.
  • Driveway and Sod restorations ongoing. To be completed by Early December.
  • Due to unfavorable temperatures for paving, road resurfacing is likely to be postponed until spring 2025. However, if an unseasonably warm day occurs in December, paving may proceed at that time. As it stands, the work is tentatively scheduled for spring 2025.


Project Update #5- Clearmeadow Boulevard (Week of November 18th)

  • Curb removal and replacements are ongoing throughout Clearmeadow. Anticipated to be completed this week.
  • Driveway restorations and placement of topsoil and sod will commence in the next week or two.
  • Road paving is tentatively scheduled for the next 2 weeks- weather permitting. Should weather not allow for paving this year, then paving will be deferred to Spring 2025.


Project Update #4 - Clearmeadow Boulevard (Week of November 11th)

  • Curb removal and replacements have begun throughout Clearmeadow.
  • Sidewalk removals and replacements are still underway along south side of Clearmeadow. The majority of the north side sidewalk work has been completed.
  • After completion of curb and sidewalk work, road grinding and manhole adjustments will begin- anticipated to start in 1-2 weeks, weather permitting.


Project Update #3 - Clearmeadow Boulevard (Week of November 4th)

  • Crews have began sidewalk removal and replacements along the north side of Clearmeadow. Once complete, they will move to the south side of Clearmeadow and begin sidewalk removal and replacements on the south side.
  • After sidewalk removal and replacements are completed on the north and south sides of Clearmeadow, curb removals will begin.


Project Update #2 - Clearmeadow Boulevard (Week of October 28th)

  • Crews will begin work on Clearmeadow this week, below is a summary of the upcoming work:
  • Curb Replacement: Concrete crews will be mobilizing on-site this week to begin curb replacement work along Clearmeadow Boulevard. You may see crews saw-cutting and removing sections of curb throughout the area. This is expected to take approximately 2–3 weeks to complete.
  • Road Grinding and Manhole Adjustments: Once curb replacements are complete, the contractor will proceed with grinding the road surface and adjusting manholes to prepare for paving.
  • Sidewalk Replacements: Weather permitting, sidewalk replacements may also take place this year. If weather conditions do not allow, this work will be postponed until next year. We will keep you informed with additional updates on the timing for sidewalk replacements


Project Update #1 - Clearmeadow Boulevard

  • Please be advised that the start of Clearmeadow Boulevard Resurfacing has been slightly delayed and the project is now expected to begin in late October. We appreciate your understanding and will provide further updates as needed.
Share Project Update: Clearmeadow Boulevard on Facebook Share Project Update: Clearmeadow Boulevard on Twitter Share Project Update: Clearmeadow Boulevard on Linkedin Email Project Update: Clearmeadow Boulevard link
#<Object:0x0000000043058e10>