New Sport Pads coming to Proctor Park and Environmental Park

Share New Sport Pads coming to Proctor Park and Environmental Park on Facebook Share New Sport Pads coming to Proctor Park and Environmental Park on Twitter Share New Sport Pads coming to Proctor Park and Environmental Park on Linkedin Email New Sport Pads coming to Proctor Park and Environmental Park link

As part of the Town of Newmarket's 10-Year Recreation and Capital Plan, Sports Courts are being built at Proctor Park (Primrose Lane) and Environmental Park (Woodspring Avenue).

Thank you to the 600+ residents that provided their feedback through an online survey that ran from September to October on what sports court they want to see to built in Environmental Park and Proctor Park. See below for two future Public Consultation Meetings that you can participate in on October 17 for Proctor Park and October 21 for Environmental Park.



Virtual Public Consultation Centre Meeting for Proctor Park

Thank you to everyone who attended the Proctor Park Virtual Public Meeting on Thursday, October 17. For those who could not make it to the meeting, a video recording of the meeting can be found below:

Proctor Park Presentation

Proctor Park Questions and Answers received at the Public Meeting

See the proposed renderings for Proctor Park located on the right hand side of this page.



Virtual Public Consultation Centre Meeting for Environmental Park

Thank you to everyone who attended the Proctor Park Virtual Public Meeting on Monday, October 21. For those who could not make it to the meeting, a video recording of the meeting can be found below:

Environmental Park Presentation

Environmental Park Questions and Answers received at the Public Meeting

See the proposed renderings for Environmental Park located on the right hand side of this page.

Proctor Park (Primrose Lane)

Environmental Park (Woodspring Avenue)


This project aligns with Newmarket's Council Priories in creating spaces and places.

As part of the Town of Newmarket's 10-Year Recreation and Capital Plan, Sports Courts are being built at Proctor Park (Primrose Lane) and Environmental Park (Woodspring Avenue).

Thank you to the 600+ residents that provided their feedback through an online survey that ran from September to October on what sports court they want to see to built in Environmental Park and Proctor Park. See below for two future Public Consultation Meetings that you can participate in on October 17 for Proctor Park and October 21 for Environmental Park.



Virtual Public Consultation Centre Meeting for Proctor Park

Thank you to everyone who attended the Proctor Park Virtual Public Meeting on Thursday, October 17. For those who could not make it to the meeting, a video recording of the meeting can be found below:

Proctor Park Presentation

Proctor Park Questions and Answers received at the Public Meeting

See the proposed renderings for Proctor Park located on the right hand side of this page.



Virtual Public Consultation Centre Meeting for Environmental Park

Thank you to everyone who attended the Proctor Park Virtual Public Meeting on Monday, October 21. For those who could not make it to the meeting, a video recording of the meeting can be found below:

Environmental Park Presentation

Environmental Park Questions and Answers received at the Public Meeting

See the proposed renderings for Environmental Park located on the right hand side of this page.

Proctor Park (Primrose Lane)

Environmental Park (Woodspring Avenue)


This project aligns with Newmarket's Council Priories in creating spaces and places.

  • Environmental Park Sport Court Update

    Share Environmental Park Sport Court Update on Facebook Share Environmental Park Sport Court Update on Twitter Share Environmental Park Sport Court Update on Linkedin Email Environmental Park Sport Court Update link

    October 2024 - Construction underway. Please note that the site will remain fenced off but the park will remain open. The access through Woodspring is temporarily blocked. Please use the entrance through Gilpin Dr.


    November 2024 - Tree Spalding completed. Asphalt base lift underway.


    December 2024 - Base lift for asphalt is completed. The fence will remain around the court construction area until late spring 2025. If you see any fencing that is knocked down, or you see anyone entering the fenced area, please call the town to open a ticket or send an email to dsakrani@newmarket.ca. Please note that the access through Woodspring will remain closed until the park is completed. Please use the access through Gilpin, which connects to the rest of the park. For your safety, please avoid the construction area.


    April 2025 - Contractor back on site, doing site maintenance. Fences may go down while the contractor cleans up the site. Please note the park is not open.


    May 2025 - Second lift of asphalt underway and to be completed soon. Equipment installation to take place, as well as sod placement.


    June 2025 - Defiency work underway. Please note that the town has to remove nets due to unauthorized access to the courts by young kids. Courts remain closed.


    July 2025 - Contractor back on site conducting deficiency repairs.


  • Proctor Park Construction Updates

    Share Proctor Park Construction Updates on Facebook Share Proctor Park Construction Updates on Twitter Share Proctor Park Construction Updates on Linkedin Email Proctor Park Construction Updates link

    October 2024 - Construction underway. Please note that the site will remain fenced off but the park will remain open.


    November 2024 - Asphalt base lift underway. Please note that the entrance to the park may temporarily be inaccessible for very brief periods during the construction due to large trucks entering and leaving site.


    December 2024 - Base lift for asphalt is completed. The fence will remain around the court construction area until late spring 2025. If you see any fencing that is knocked down, or you see anyone entering the fenced area, please call the town or send an email to dsakrani@newmarket.ca. Please note that the asphalt trail is not maintained in the winter. For your safety, please avoid the construction area.


    April 2025 - Contractor back on site, doing site maintenance. Fences may go down while the contractor cleans up the site. Please note the park is not open.


    May 2025 - Second lift of asphalt underway and to be completed soon. Equipment installation to take place, as well as sod placement.


    June 2025 - Defiency work underway. Please note that the town has to remove nets due to unauthorized access to the courts by young kids. Courts remain closed.


    July 2025 - Contractor back on site conducting deficiency repairs.