Stickwood Court Reconstruction

Share Stickwood Court Reconstruction on Facebook Share Stickwood Court Reconstruction on X (formerly Twitter) Share Stickwood Court Reconstruction on Linkedin Email Stickwood Court Reconstruction link

The Town of Newmarket is reconstructing Stickwood Court. This work includes full reconstruction from Srigley Street to the end of the cul-de-sac, featuring watermain replacement and rehabilitation of the sanitary sewer at the Srigley Street intersection. Stormwater improvements, including a new catch basin, will enhance drainage performance.

The roadway will be reconstructed with new pavement, curb, and gutter, and streetlight will be upgraded.

This work will improve service reliability, drainage, and overall safety while bringing the street up to current Town standards.

Construction is expected to start Summer 2026.

Public Consultation Centre (PCC): Stickwood Court Reconstruction Public Consultation Centre

The Town of Newmarket would like to thank all residents who participated in the Public Consultation Centre (PCC) and Public Information Centre (PIC) for the Stickwood Court Reconstruction Project.

Residents can view the presentation materials in the Documents section below for additional information about the project.

The Town of Newmarket is reconstructing Stickwood Court. This work includes full reconstruction from Srigley Street to the end of the cul-de-sac, featuring watermain replacement and rehabilitation of the sanitary sewer at the Srigley Street intersection. Stormwater improvements, including a new catch basin, will enhance drainage performance.

The roadway will be reconstructed with new pavement, curb, and gutter, and streetlight will be upgraded.

This work will improve service reliability, drainage, and overall safety while bringing the street up to current Town standards.

Construction is expected to start Summer 2026.

Public Consultation Centre (PCC): Stickwood Court Reconstruction Public Consultation Centre

The Town of Newmarket would like to thank all residents who participated in the Public Consultation Centre (PCC) and Public Information Centre (PIC) for the Stickwood Court Reconstruction Project.

Residents can view the presentation materials in the Documents section below for additional information about the project.

  • Construction Update - October 2026

    Share Construction Update - October 2026 on Facebook Share Construction Update - October 2026 on X (formerly Twitter) Share Construction Update - October 2026 on Linkedin Email Construction Update - October 2026 link

    The Town of Newmarket has completed the installation and commissioning of the temporary watermain for the Stickwood Court Reconstruction Project.

    Construction activities will continue, with watermain installation scheduled to begin on Monday, October 19, 2026.

    The Town appreciates residents' patience and understanding as work progresses.

    The Town of Newmarket has completed the installation and commissioning of the temporary watermain for the Stickwood Court Reconstruction Project.

    Construction activities will continue, with watermain installation scheduled to begin on Monday, October 19, 2026.

    The Town appreciates residents' patience and understanding as work progresses.

  • Notice of Construction

    Share Notice of Construction on Facebook Share Notice of Construction on X (formerly Twitter) Share Notice of Construction on Linkedin Email Notice of Construction link

    Stickwood Court Reconstruction

    The Town of Newmarket will be undertaking reconstruction work on Stickwood Court which will consist of watermain, water service and storm sewer improvements. The road and concrete curbs will also be reconstructed once the underground work is complete.

    Anticipated Schedule

    Construction will commence in September with completion scheduled for late Summer 2027. Underground infrastructure work will be completed by the end of this year. Disturbed portions of the roadway will be temporarily patched for the winter, with road reconstruction, concrete, asphalt paving and final restoration anticipated to commence in the Spring 2027.

    Residential Access

    Access to Stickwood Court and residential properties will be maintained to the greatest extent possible during construction. Temporary driveway restrictions may occasionally be required, and affected residents will be provided with advance notice. Delivery services and emergency vehicle access will also be maintained.

    Temporary Water Disruptions

    To facilitate the change from the old to the new watermain, temporary water shutoffs will also be required at various stages of construction. Residents affected by a planned water shutoff will receive a minimum of 72 hours' advance notice.

    What to Expect

    • The Town and Contractor recognize that construction can be disruptive and will make every reasonable effort to minimize inconvenience. During construction, residents may experience:
    • Construction equipment, dust, vibration and noise associated with construction activities.
    • Garbage, recycling and organics collection will continue as scheduled. If collection procedures change residents will be notified in advance.
    • Construction working hours will be limited to 7am to 7pm

    We appreciate that construction sites and equipment can be an attractive play area for kids after working hours, we kindly ask parents to refrain from allowing their kids to play in the work site. We appreciate your patience and cooperation while these important infrastructure improvements are completed.

    Stickwood Court Reconstruction

    The Town of Newmarket will be undertaking reconstruction work on Stickwood Court which will consist of watermain, water service and storm sewer improvements. The road and concrete curbs will also be reconstructed once the underground work is complete.

    Anticipated Schedule

    Construction will commence in September with completion scheduled for late Summer 2027. Underground infrastructure work will be completed by the end of this year. Disturbed portions of the roadway will be temporarily patched for the winter, with road reconstruction, concrete, asphalt paving and final restoration anticipated to commence in the Spring 2027.

    Residential Access

    Access to Stickwood Court and residential properties will be maintained to the greatest extent possible during construction. Temporary driveway restrictions may occasionally be required, and affected residents will be provided with advance notice. Delivery services and emergency vehicle access will also be maintained.

    Temporary Water Disruptions

    To facilitate the change from the old to the new watermain, temporary water shutoffs will also be required at various stages of construction. Residents affected by a planned water shutoff will receive a minimum of 72 hours' advance notice.

    What to Expect

    • The Town and Contractor recognize that construction can be disruptive and will make every reasonable effort to minimize inconvenience. During construction, residents may experience:
    • Construction equipment, dust, vibration and noise associated with construction activities.
    • Garbage, recycling and organics collection will continue as scheduled. If collection procedures change residents will be notified in advance.
    • Construction working hours will be limited to 7am to 7pm

    We appreciate that construction sites and equipment can be an attractive play area for kids after working hours, we kindly ask parents to refrain from allowing their kids to play in the work site. We appreciate your patience and cooperation while these important infrastructure improvements are completed.