Mulock Multi Use Path
Consultation has concluded and the project was completed and opened in Summer 2026.
Opened in summer 2026, the Town of Newmarket and York Region built a multi-use path (MUP) along Mulock Drive that runs from Bathurst Street to Harry Walker Parkway. This east-west path was designed to allow for a wide-range of recreational uses such as cycling, walking, jogging and wheelchair access.
The goal for the Mulock Drive MUP is to allow the community to connect to key destinations in Town such as existing trails, schools, the Magna Centre and the Mulock Park (opening later this summer).
View the flyover view below to see the trajectory of the MUP.
The Mulock MUP project has a three-meter-wide trail, where feasible, in the boulevard of Mulock Drive from Bathurst Street to Harry Walker Parkway and is expected to be completed in two phases. See below for more information on the construction phase. The project is being jointly funded by the Town of Newmarket and Region of York through development charges.
Phase 1: Bathurst Street to Yonge Street (Starting the week of May 8 Expected completion: End of Fall 2023 subject to weather and site conditions)
- A new asphalt multi-use path will be constructed in place of the concrete sidewalk along the south side of Mulock Drive from Bathurst Street to Doubletree Lane and along the north side of Mulock Drive from Doubletree Lane to Yonge Street.
- Work includes concrete and asphalt removal, installation of new asphalt and concrete paths, grading, planting, guardrail adjustments, sign relocations, and sodding.
- During construction, a lane shift will occur to accommodate the work and to ensure minimal disruption to traffic. Please follow the signs posted from Yonge Street to Doubletree Lane.
- The sidewalk on the north side of Mulock Drive from Yonge Street to Doubletree Lane will also be closed to pedestrians for the duration of the first phase of construction.
We apologize for any inconvenience this project may cause and thank you for your patience while we complete this exciting MUP project that will improve our active transportation network and provide a safe direct route to the future Mulock Park.
If you have any questions about the project, please use the 'question' section below.
Phase 2: Yonge Street to Harry Walker Parkway- May 2025 - June 2026
Consultation has concluded and the project was completed and opened in Summer 2026.
Have a question about the project? Let us know and we will get back to you as soon as possible.