Road Resurfacing Projects
2026 Road Resurfacing Projects
The Town of Newmarket will be undertaking multiple road resurfacing projects in 2026. These projects will include grinding and resurfacing of the roadway, line painting, catch basin repairs, curb and sidewalk repairs and accessibility improvements.
Construction is anticipated to begin in the summer months, with traffic access to homes and businesses maintained throughout the duration of the work. Advance notice will be provided to residents regarding timelines and any potential disruptions to driveway access.
Please see below for the project locations and refer to the Project Updates section on the right-hand side of this page for the latest information.
____________________________________________________________________________________________________________________
Construction on Stellar Drive will begin on Monday, November 9, 2026.
What to Expect During Construction
- Grinding and paving operations planned for overnight and/or weekends
- Construction noise, dust and vibration
- Heavy machinery and trucks operating within the work area
- Lane restrictions and temporary traffic delays
- Dump trucks coming and leaving the site
- Temporary driveway interruptions
- Emergency services and garbage/recycling collection will be maintained

Sandford Street
Project has been completed.

Columbus Way - Summer 2027
Work on Columbus Way is anticipated to begin in summer 2027. Please check back for updates.

Sawmill Valley Drive - Summer 2027
Work on Sawmill Valley Drive is anticipated to begin in Summer 2027. Please check back for updates.

______________________________________________________________________________________________________________________
Work on Eagle Street is anticipated to begin in Summer of 2027. Please check back for updates.

______________________________________________________________________________________________________________
Gorham Street
This project has been completed.

2026 Road Resurfacing Projects
The Town of Newmarket will be undertaking multiple road resurfacing projects in 2026. These projects will include grinding and resurfacing of the roadway, line painting, catch basin repairs, curb and sidewalk repairs and accessibility improvements.
Construction is anticipated to begin in the summer months, with traffic access to homes and businesses maintained throughout the duration of the work. Advance notice will be provided to residents regarding timelines and any potential disruptions to driveway access.
Please see below for the project locations and refer to the Project Updates section on the right-hand side of this page for the latest information.
____________________________________________________________________________________________________________________
Construction on Stellar Drive will begin on Monday, November 9, 2026.
What to Expect During Construction
- Grinding and paving operations planned for overnight and/or weekends
- Construction noise, dust and vibration
- Heavy machinery and trucks operating within the work area
- Lane restrictions and temporary traffic delays
- Dump trucks coming and leaving the site
- Temporary driveway interruptions
- Emergency services and garbage/recycling collection will be maintained

Sandford Street
Project has been completed.

Columbus Way - Summer 2027
Work on Columbus Way is anticipated to begin in summer 2027. Please check back for updates.

Sawmill Valley Drive - Summer 2027
Work on Sawmill Valley Drive is anticipated to begin in Summer 2027. Please check back for updates.

______________________________________________________________________________________________________________________
Work on Eagle Street is anticipated to begin in Summer of 2027. Please check back for updates.

______________________________________________________________________________________________________________
Gorham Street
This project has been completed.

-
Eagle Street Resurfacing
Share Eagle Street Resurfacing on Facebook Share Eagle Street Resurfacing on X (formerly Twitter) Share Eagle Street Resurfacing on Linkedin Email Eagle Street Resurfacing linkEagle Street Resurfacing
The Town of Newmarket is pleased to advise that Eagle Street Resurfacing is scheduled to begin on November 19th, with work anticipated to be completed by December 2026. The Town’s contractor, Forest Paving, has commenced preparation work for resurfacing, with on-site inspection provided by Gannet Flemming (GFT).
Scope of Work
- Remove and replacement of deficient sidewalk bays
- Remove and replacement of deficient curb and gutter
- Adjustments of manholes, catch basins and water valves.
- Grinding of asphalt scheduled for November 19th
- Paving of surface asphalt scheduled for November 23rd
What to Expect During Construction
- Typical work hours will be from Monday to Friday between 7 a.m. – 7 p.m.
- Weekend and/ or nightwork may be required
- Noise, dust, and minor vibration
- Garbage and recycling collection will continue
- Temporary driveway and service restrictions with advanced notice
- The road will be limited to local-traffic only
- Access to business will remain open at all times
- York Region transit busses, garbage pick-up and emergency access will be maintained throughout construction.
Grinding and paving remains dependent on weather. The Town intends to complete the paving works in 2026, however, should weather conditions become unfavorable, the Town will defer paving until spring 2027.
Project Benefits
This work will improve the condition of the road surface and extend its life. New pavement, sidewalk repairs, and curb upgrades will create a smoother, safer, and more accessible experience for road users.
We appreciate your patience during this important upgrade.
Eagle Street Resurfacing
The Town of Newmarket is pleased to advise that Eagle Street Resurfacing is scheduled to begin on November 19th, with work anticipated to be completed by December 2026. The Town’s contractor, Forest Paving, has commenced preparation work for resurfacing, with on-site inspection provided by Gannet Flemming (GFT).
Scope of Work
- Remove and replacement of deficient sidewalk bays
- Remove and replacement of deficient curb and gutter
- Adjustments of manholes, catch basins and water valves.
- Grinding of asphalt scheduled for November 19th
- Paving of surface asphalt scheduled for November 23rd
What to Expect During Construction
- Typical work hours will be from Monday to Friday between 7 a.m. – 7 p.m.
- Weekend and/ or nightwork may be required
- Noise, dust, and minor vibration
- Garbage and recycling collection will continue
- Temporary driveway and service restrictions with advanced notice
- The road will be limited to local-traffic only
- Access to business will remain open at all times
- York Region transit busses, garbage pick-up and emergency access will be maintained throughout construction.
Grinding and paving remains dependent on weather. The Town intends to complete the paving works in 2026, however, should weather conditions become unfavorable, the Town will defer paving until spring 2027.
Project Benefits
This work will improve the condition of the road surface and extend its life. New pavement, sidewalk repairs, and curb upgrades will create a smoother, safer, and more accessible experience for road users.
We appreciate your patience during this important upgrade.
-
Stellar Drive Resurfacing
Share Stellar Drive Resurfacing on Facebook Share Stellar Drive Resurfacing on X (formerly Twitter) Share Stellar Drive Resurfacing on Linkedin Email Stellar Drive Resurfacing linkStellar Drive Resurfacing
The Town of Newmarket is pleased to announce that Forest Contractors Ltd. has been awarded the road resurfacing project on Stellar Drive, between Leslie Street and Harry Walker Parkway. The roadway works is scheduled to commence November 9, 2026, with expected completion by the end of the year, weather permitting. The work will include roadway grinding, manhole adjustments, asphalt paving, line painting and site restoration. If weather conditions are unfavourable, these activities may be postponed until 2027.
Motorists are asked to reduce their speed, drive with caution, and follow all posted signage when travelling through the construction area.
What to Expect During Construction
- Grinding and paving operations planned for overnight and/or weekends
- Construction noise, dust and vibration
- Heavy machinery and trucks operating within the work area
- Lane restrictions and temporary traffic delays
- Dump trucks coming and leaving the site
- Temporary driveway interruptions
- Emergency services and garbage/recycling collection will be maintained
Project Benefits
This project will renew the roadway and extend the existing service life of the road infrastructure. It will also enhance driving conditions and improve pavement marking visibility.
The Town appreciates your continued cooperation and patience as we complete the work safely and efficiently.
Stellar Drive Resurfacing
The Town of Newmarket is pleased to announce that Forest Contractors Ltd. has been awarded the road resurfacing project on Stellar Drive, between Leslie Street and Harry Walker Parkway. The roadway works is scheduled to commence November 9, 2026, with expected completion by the end of the year, weather permitting. The work will include roadway grinding, manhole adjustments, asphalt paving, line painting and site restoration. If weather conditions are unfavourable, these activities may be postponed until 2027.
Motorists are asked to reduce their speed, drive with caution, and follow all posted signage when travelling through the construction area.
What to Expect During Construction
- Grinding and paving operations planned for overnight and/or weekends
- Construction noise, dust and vibration
- Heavy machinery and trucks operating within the work area
- Lane restrictions and temporary traffic delays
- Dump trucks coming and leaving the site
- Temporary driveway interruptions
- Emergency services and garbage/recycling collection will be maintained
Project Benefits
This project will renew the roadway and extend the existing service life of the road infrastructure. It will also enhance driving conditions and improve pavement marking visibility.
The Town appreciates your continued cooperation and patience as we complete the work safely and efficiently.
-
Construction Update - Gorham Street Resurfacing -August 6, 2026
Share Construction Update - Gorham Street Resurfacing -August 6, 2026 on Facebook Share Construction Update - Gorham Street Resurfacing -August 6, 2026 on X (formerly Twitter) Share Construction Update - Gorham Street Resurfacing -August 6, 2026 on Linkedin Email Construction Update - Gorham Street Resurfacing -August 6, 2026 linkGorham Street Resurfacing
The Town of Newmarket has retained IPAC Paving to complete the asphalt resurfacing
of Gorham Street between Leslie Street and Harry Walker Parkway on Saturday, August 8, 2026.
Construction Schedule
• Date: Saturday, August 8, 2026
• Work Start Time: 7 a.m.
• Paving is anticipated to be completed on August 8, 2026, weather permitting.To prepare for paving operations, the contractor will complete minor preparatory work in advance of paving. This work may include mobilization, roadway adjustments, and traffic control setup. These activities are not expected to impact driveway access; however, motorists are asked to exercise caution when travelling through the work area.
What to Expect During Construction
• Temporary traffic delays and lane restrictions.
• Minor construction-related noise, dust, and vibrations.
• Temporary interruptions to driveway access while asphalt is being placed in front of driveways.
• Heavy construction equipment and trucks operating throughout the work zone.Important Information
• Please refrain from driving or walking on freshly placed asphalt until the barricades have been removed by the work crews.
• Paving will be completed one lane at a time, with the opposite lane remaining open to traffic. Please follow all traffic control signage and directions from traffic control personnel.
• If access to your driveway or entrance is temporarily restricted during paving operations, crews will restore access as quickly and safely as possible.
• Temporary No Parking restrictions will be in effect during construction hours. We kindly ask that all vehicles be parked off the street to help avoid delays.The Town appreciates your patience and cooperation while these improvements are being completed. Every effort will be made to minimize inconvenience and complete the work as quickly and safely as possible. If work is delayed due to weather or unforeseen circumstances, paving will be rescheduled to the next suitable construction day.
Gorham Street Resurfacing
The Town of Newmarket has retained IPAC Paving to complete the asphalt resurfacing
of Gorham Street between Leslie Street and Harry Walker Parkway on Saturday, August 8, 2026.
Construction Schedule
• Date: Saturday, August 8, 2026
• Work Start Time: 7 a.m.
• Paving is anticipated to be completed on August 8, 2026, weather permitting.To prepare for paving operations, the contractor will complete minor preparatory work in advance of paving. This work may include mobilization, roadway adjustments, and traffic control setup. These activities are not expected to impact driveway access; however, motorists are asked to exercise caution when travelling through the work area.
What to Expect During Construction
• Temporary traffic delays and lane restrictions.
• Minor construction-related noise, dust, and vibrations.
• Temporary interruptions to driveway access while asphalt is being placed in front of driveways.
• Heavy construction equipment and trucks operating throughout the work zone.Important Information
• Please refrain from driving or walking on freshly placed asphalt until the barricades have been removed by the work crews.
• Paving will be completed one lane at a time, with the opposite lane remaining open to traffic. Please follow all traffic control signage and directions from traffic control personnel.
• If access to your driveway or entrance is temporarily restricted during paving operations, crews will restore access as quickly and safely as possible.
• Temporary No Parking restrictions will be in effect during construction hours. We kindly ask that all vehicles be parked off the street to help avoid delays.The Town appreciates your patience and cooperation while these improvements are being completed. Every effort will be made to minimize inconvenience and complete the work as quickly and safely as possible. If work is delayed due to weather or unforeseen circumstances, paving will be rescheduled to the next suitable construction day.
-
Project Update - Savage Road - Completed September 2025
Share Project Update - Savage Road - Completed September 2025 on Facebook Share Project Update - Savage Road - Completed September 2025 on X (formerly Twitter) Share Project Update - Savage Road - Completed September 2025 on Linkedin Email Project Update - Savage Road - Completed September 2025 linkCLOSED: This discussion has concluded.Project Update #6 - September 18th 2025
Recent work completed:
All road work has been completed.
Restoration work for the interlock driveways are to take place starting this week.
Sod restoration will begin shortly after, likely early October
What to expect over the next 2 weeks:
Various interlock driveways are to be restored
Sod will be placed in areas where sidewalk work occurred
Project Update #5 - September 4th 2025
Recent work completed:
Road resurfacing work has been completed
Majority of line painting has been completed
What to expect over the next 2 weeks:
Various interlock driveways are to be restored
Continued line painting work for some crosswalks and urban shoulders
Sod will be placed in areas where sidewalk work occurred
Project Update #4 - August 12th 2025
Recent work completed:
All sidewalk work has been completed.
Boulevard areas where sidewalk have been replaced have been backfilled with topsoil in preparation of sod.
Curb removal and replacement work has begun
What to expect over the next 2 weeks:
Continued removal and replacement of curb
Following curb work, asphalt grinding and driveway paving will commence
Project Update #3 - July 29th 2025
Recent work completed:
Majority of sidewalk work has been completed along the south side of Savage Road.
Boulevard areas where sidewalk have been replaced have been backfilled with topsoil in preparation of sod.
What to expect over the next 2 weeks:
Continued removal and replacement of sidewalks along the north side.
Start of curb removals at residential and commercial driveways, following the sidewalk work.
Project Update #2 - July 18th 2025
Construction on Savage Road is underway. Recent work completed:
Saw cutting of existing curbs and sidewalks to prepare for removal and replacement.
Sidewalk removals have begun along the south side of Savage Road.
Curb removals and replacements are underway, starting mainly at intersections to maintain accessibility.
What to expect over the next 2 weeks:
Continued removal and replacement of sidewalks.
Construction equipment and crews will remain active in the area; please use caution and follow posted signage.
Temporary pedestrian detours may be in place while work is ongoing.
Project Update #1 - July 11th 2025
Construction on Savage Road is scheduled to begin in July 2025. Over the next few weeks, residents will notice the placement of construction barrels and traffic control signage along the roadway.
What to expect in the coming weeks:
Saw cutting of curbs and sidewalks will begin shortly after initial setup in preparation for removal.
Pedestrian access will be maintained on at least one side of the road at all times.
Short term disruptions to driveway access may occur during curb and sidewalk work. Notice will be provided to residents in advance.
Emergency access will be maintained at all times.
Project Update #6 - September 18th 2025
Recent work completed:
All road work has been completed.
Restoration work for the interlock driveways are to take place starting this week.
Sod restoration will begin shortly after, likely early October
What to expect over the next 2 weeks:
Various interlock driveways are to be restored
Sod will be placed in areas where sidewalk work occurred
Project Update #5 - September 4th 2025
Recent work completed:
Road resurfacing work has been completed
Majority of line painting has been completed
What to expect over the next 2 weeks:
Various interlock driveways are to be restored
Continued line painting work for some crosswalks and urban shoulders
Sod will be placed in areas where sidewalk work occurred
Project Update #4 - August 12th 2025
Recent work completed:
All sidewalk work has been completed.
Boulevard areas where sidewalk have been replaced have been backfilled with topsoil in preparation of sod.
Curb removal and replacement work has begun
What to expect over the next 2 weeks:
Continued removal and replacement of curb
Following curb work, asphalt grinding and driveway paving will commence
Project Update #3 - July 29th 2025
Recent work completed:
Majority of sidewalk work has been completed along the south side of Savage Road.
Boulevard areas where sidewalk have been replaced have been backfilled with topsoil in preparation of sod.
What to expect over the next 2 weeks:
Continued removal and replacement of sidewalks along the north side.
Start of curb removals at residential and commercial driveways, following the sidewalk work.
Project Update #2 - July 18th 2025
Construction on Savage Road is underway. Recent work completed:
Saw cutting of existing curbs and sidewalks to prepare for removal and replacement.
Sidewalk removals have begun along the south side of Savage Road.
Curb removals and replacements are underway, starting mainly at intersections to maintain accessibility.
What to expect over the next 2 weeks:
Continued removal and replacement of sidewalks.
Construction equipment and crews will remain active in the area; please use caution and follow posted signage.
Temporary pedestrian detours may be in place while work is ongoing.
Project Update #1 - July 11th 2025
Construction on Savage Road is scheduled to begin in July 2025. Over the next few weeks, residents will notice the placement of construction barrels and traffic control signage along the roadway.
What to expect in the coming weeks:
Saw cutting of curbs and sidewalks will begin shortly after initial setup in preparation for removal.
Pedestrian access will be maintained on at least one side of the road at all times.
Short term disruptions to driveway access may occur during curb and sidewalk work. Notice will be provided to residents in advance.
Emergency access will be maintained at all times.
-
Project Update - Gorham Street
Share Project Update - Gorham Street on Facebook Share Project Update - Gorham Street on X (formerly Twitter) Share Project Update - Gorham Street on Linkedin Email Project Update - Gorham Street linkCLOSED: This discussion has concluded.Work on Gorham is anticipated to begin August 2025.
Work on Gorham is anticipated to begin August 2025.
-
Project Update: Clearmeadow Boulevard - Completed August 2025
Share Project Update: Clearmeadow Boulevard - Completed August 2025 on Facebook Share Project Update: Clearmeadow Boulevard - Completed August 2025 on X (formerly Twitter) Share Project Update: Clearmeadow Boulevard - Completed August 2025 on Linkedin Email Project Update: Clearmeadow Boulevard - Completed August 2025 linkCLOSED: This discussion has concluded.Project Update #11- Clearmeadow Boulevard (Week of August 11th 2025)
- Road resurfacing has been completed
- Majority of line painting completed, with some remaining crosswalks and stop bars to be painted
Project Update #10- Clearmeadow Boulevard (Week of August 4th 2025)
- Road resurfacing will take place August 5th and 6th
- After resurfacing work, line painting will commence
Project Update #9- Clearmeadow Boulevard (Week of July 28th 2025)
- Road grinding has been completed
- Manhole adjustments have been completed
- Base Asphalt repairs are scheduled for this week
- Road Resurfacing is anticipated to begin later this week (Week of July 28th) or early next week (Week of August 4th), weather permitting
Project Update #8- Clearmeadow Boulevard (Week of July 21st 2025)
- Road grinding has begun in preparation for resurfacing work
- After grinding work, manhole adjustments will take place
- Resurfacing is expected to take place in in the following week (week of July 28th), weather permitting
Project Update #7- Clearmeadow Boulevard (Week of December 2nd)
- Due to unfavorable temperatures for paving, road resurfacing is postponed until summer 2025.
- Driveway and boulevard restorations ongoing. To be completed by Early December (likely late this week or early next week)
- A review of the resorted areas will be done in Spring 2025, and any areas that are not completed to the Towns satisfaction will be replaced.
Project Update #6- Clearmeadow Boulevard (Week of November 25th)
- Curb removal and replacements are complete.
- Driveway and Sod restorations ongoing. To be completed by Early December.
- Due to unfavorable temperatures for paving, road resurfacing is likely to be postponed until spring 2025. However, if an unseasonably warm day occurs in December, paving may proceed at that time. As it stands, the work is tentatively scheduled for spring 2025.
Project Update #5- Clearmeadow Boulevard (Week of November 18th)
- Curb removal and replacements are ongoing throughout Clearmeadow. Anticipated to be completed this week.
- Driveway restorations and placement of topsoil and sod will commence in the next week or two.
- Road paving is tentatively scheduled for the next 2 weeks- weather permitting. Should weather not allow for paving this year, then paving will be deferred to Spring 2025.
Project Update #4 - Clearmeadow Boulevard (Week of November 11th)
- Curb removal and replacements have begun throughout Clearmeadow.
- Sidewalk removals and replacements are still underway along south side of Clearmeadow. The majority of the north side sidewalk work has been completed.
- After completion of curb and sidewalk work, road grinding and manhole adjustments will begin- anticipated to start in 1-2 weeks, weather permitting.
Project Update #3 - Clearmeadow Boulevard (Week of November 4th)
- Crews have began sidewalk removal and replacements along the north side of Clearmeadow. Once complete, they will move to the south side of Clearmeadow and begin sidewalk removal and replacements on the south side.
- After sidewalk removal and replacements are completed on the north and south sides of Clearmeadow, curb removals will begin.
Project Update #2 - Clearmeadow Boulevard (Week of October 28th)
- Crews will begin work on Clearmeadow this week, below is a summary of the upcoming work:
- Curb Replacement: Concrete crews will be mobilizing on-site this week to begin curb replacement work along Clearmeadow Boulevard. You may see crews saw-cutting and removing sections of curb throughout the area. This is expected to take approximately 2–3 weeks to complete.
- Road Grinding and Manhole Adjustments: Once curb replacements are complete, the contractor will proceed with grinding the road surface and adjusting manholes to prepare for paving.
- Sidewalk Replacements: Weather permitting, sidewalk replacements may also take place this year. If weather conditions do not allow, this work will be postponed until next year. We will keep you informed with additional updates on the timing for sidewalk replacements
Project Update #1 - Clearmeadow Boulevard
- Please be advised that the start of Clearmeadow Boulevard Resurfacing has been slightly delayed and the project is now expected to begin in late October. We appreciate your understanding and will provide further updates as needed.
Project Update #11- Clearmeadow Boulevard (Week of August 11th 2025)
- Road resurfacing has been completed
- Majority of line painting completed, with some remaining crosswalks and stop bars to be painted
Project Update #10- Clearmeadow Boulevard (Week of August 4th 2025)
- Road resurfacing will take place August 5th and 6th
- After resurfacing work, line painting will commence
Project Update #9- Clearmeadow Boulevard (Week of July 28th 2025)
- Road grinding has been completed
- Manhole adjustments have been completed
- Base Asphalt repairs are scheduled for this week
- Road Resurfacing is anticipated to begin later this week (Week of July 28th) or early next week (Week of August 4th), weather permitting
Project Update #8- Clearmeadow Boulevard (Week of July 21st 2025)
- Road grinding has begun in preparation for resurfacing work
- After grinding work, manhole adjustments will take place
- Resurfacing is expected to take place in in the following week (week of July 28th), weather permitting
Project Update #7- Clearmeadow Boulevard (Week of December 2nd)
- Due to unfavorable temperatures for paving, road resurfacing is postponed until summer 2025.
- Driveway and boulevard restorations ongoing. To be completed by Early December (likely late this week or early next week)
- A review of the resorted areas will be done in Spring 2025, and any areas that are not completed to the Towns satisfaction will be replaced.
Project Update #6- Clearmeadow Boulevard (Week of November 25th)
- Curb removal and replacements are complete.
- Driveway and Sod restorations ongoing. To be completed by Early December.
- Due to unfavorable temperatures for paving, road resurfacing is likely to be postponed until spring 2025. However, if an unseasonably warm day occurs in December, paving may proceed at that time. As it stands, the work is tentatively scheduled for spring 2025.
Project Update #5- Clearmeadow Boulevard (Week of November 18th)
- Curb removal and replacements are ongoing throughout Clearmeadow. Anticipated to be completed this week.
- Driveway restorations and placement of topsoil and sod will commence in the next week or two.
- Road paving is tentatively scheduled for the next 2 weeks- weather permitting. Should weather not allow for paving this year, then paving will be deferred to Spring 2025.
Project Update #4 - Clearmeadow Boulevard (Week of November 11th)
- Curb removal and replacements have begun throughout Clearmeadow.
- Sidewalk removals and replacements are still underway along south side of Clearmeadow. The majority of the north side sidewalk work has been completed.
- After completion of curb and sidewalk work, road grinding and manhole adjustments will begin- anticipated to start in 1-2 weeks, weather permitting.
Project Update #3 - Clearmeadow Boulevard (Week of November 4th)
- Crews have began sidewalk removal and replacements along the north side of Clearmeadow. Once complete, they will move to the south side of Clearmeadow and begin sidewalk removal and replacements on the south side.
- After sidewalk removal and replacements are completed on the north and south sides of Clearmeadow, curb removals will begin.
Project Update #2 - Clearmeadow Boulevard (Week of October 28th)
- Crews will begin work on Clearmeadow this week, below is a summary of the upcoming work:
- Curb Replacement: Concrete crews will be mobilizing on-site this week to begin curb replacement work along Clearmeadow Boulevard. You may see crews saw-cutting and removing sections of curb throughout the area. This is expected to take approximately 2–3 weeks to complete.
- Road Grinding and Manhole Adjustments: Once curb replacements are complete, the contractor will proceed with grinding the road surface and adjusting manholes to prepare for paving.
- Sidewalk Replacements: Weather permitting, sidewalk replacements may also take place this year. If weather conditions do not allow, this work will be postponed until next year. We will keep you informed with additional updates on the timing for sidewalk replacements
Project Update #1 - Clearmeadow Boulevard
- Please be advised that the start of Clearmeadow Boulevard Resurfacing has been slightly delayed and the project is now expected to begin in late October. We appreciate your understanding and will provide further updates as needed.
-
Project Update - Bristol Road - Completed December 2025
Share Project Update - Bristol Road - Completed December 2025 on Facebook Share Project Update - Bristol Road - Completed December 2025 on X (formerly Twitter) Share Project Update - Bristol Road - Completed December 2025 on Linkedin Email Project Update - Bristol Road - Completed December 2025 linkCLOSED: This discussion has concluded.Project Update #7 - Bristol Road (Week of December 2nd)
- Paving of Bristol Road, Jack Rettie Court and Ashworth Drive have been completed
Work scheduled for the next two weeks:
- Placement of temporary line painting. Permanent line painting will be completed in Spring of 2025
- Minor restoration work where sidewalks were replaced
Project Update #6 - Bristol Road (Week of November 18th)
- Asphalt grinding has finished on Bristol Road
- Manhole adjustments have been completed
- Driveway restorations are underway
Work scheduled for the next two weeks:
- Repairing base course asphalt
- Paving
- Line painting of newly paved road
Project Update #5 - Bristol Road (Week of November 11th)
- Asphalt grinding has began on Bristol Road
- Manhole adjustments are taking place so they will be flush with new asphalt
Work scheduled for the next two weeks:
- Continuing Manhole adjustments
- Continuing Asphalt grinding
- Paving
- Line painting of newly paved road
Project Update #4 - Bristol Road (Week of November 5th)
- All sidewalk replacements have been completed along Bristol Road
- All curb replacements have been completed
- Ashworth Drive curb and sidewalk work is complete
- Sod restorations are being completed
- As advised to residents, a 500 meter section of Bristol between Chester Ave and Main Street will have resurfacing postponed until 2025
Work scheduled for the next two weeks:
- Manhole adjustments
- Asphalt grinding and paving
- Line painting of newly paved road
Project Update #3 - Bristol Road (Week of October 21st)
- All sidewalk replacements have been completed along Bristol Road
- The majority of curb replacements have been completed
- Ashworth Drive work is under way
Work scheduled for the next two weeks:
- Top soil being placed in disturbed areas
- Asphalt grinding and paving
Project Update #2- Bristol Road (Week of September 30th):
- Sidewalks and curbs replacements have been completed along the south side of Bristol Road
- Crews are working along north side of Bristol Road and will take approximately 1-2 more weeks to complete concrete work on north side of Bristol Road
Work scheduled for the next two weeks:
- Continuing curb and sidewalk replacements on the north side of Bristol Road
- Catch basin adjustments
- Backfilling areas with topsoil to be restored with sod
Project Update #1 - Bristol Road (Week of September 9th):
- Concrete crew is onsite at Bristol Road
- Sidewalks and curbs are being removed and replaced along the south side of Bristol Road
- Sidewalks have been poured at both Dr. J.M. Denison Secondary School entrances
Work scheduled for the next two weeks:
- Move concrete work from the south side of Bristol Road to the north side
- Catch basin adjustments
Project Update #7 - Bristol Road (Week of December 2nd)
- Paving of Bristol Road, Jack Rettie Court and Ashworth Drive have been completed
Work scheduled for the next two weeks:
- Placement of temporary line painting. Permanent line painting will be completed in Spring of 2025
- Minor restoration work where sidewalks were replaced
Project Update #6 - Bristol Road (Week of November 18th)
- Asphalt grinding has finished on Bristol Road
- Manhole adjustments have been completed
- Driveway restorations are underway
Work scheduled for the next two weeks:
- Repairing base course asphalt
- Paving
- Line painting of newly paved road
Project Update #5 - Bristol Road (Week of November 11th)
- Asphalt grinding has began on Bristol Road
- Manhole adjustments are taking place so they will be flush with new asphalt
Work scheduled for the next two weeks:
- Continuing Manhole adjustments
- Continuing Asphalt grinding
- Paving
- Line painting of newly paved road
Project Update #4 - Bristol Road (Week of November 5th)
- All sidewalk replacements have been completed along Bristol Road
- All curb replacements have been completed
- Ashworth Drive curb and sidewalk work is complete
- Sod restorations are being completed
- As advised to residents, a 500 meter section of Bristol between Chester Ave and Main Street will have resurfacing postponed until 2025
Work scheduled for the next two weeks:
- Manhole adjustments
- Asphalt grinding and paving
- Line painting of newly paved road
Project Update #3 - Bristol Road (Week of October 21st)
- All sidewalk replacements have been completed along Bristol Road
- The majority of curb replacements have been completed
- Ashworth Drive work is under way
Work scheduled for the next two weeks:
- Top soil being placed in disturbed areas
- Asphalt grinding and paving
Project Update #2- Bristol Road (Week of September 30th):
- Sidewalks and curbs replacements have been completed along the south side of Bristol Road
- Crews are working along north side of Bristol Road and will take approximately 1-2 more weeks to complete concrete work on north side of Bristol Road
Work scheduled for the next two weeks:
- Continuing curb and sidewalk replacements on the north side of Bristol Road
- Catch basin adjustments
- Backfilling areas with topsoil to be restored with sod
Project Update #1 - Bristol Road (Week of September 9th):
- Concrete crew is onsite at Bristol Road
- Sidewalks and curbs are being removed and replaced along the south side of Bristol Road
- Sidewalks have been poured at both Dr. J.M. Denison Secondary School entrances
Work scheduled for the next two weeks:
- Move concrete work from the south side of Bristol Road to the north side
- Catch basin adjustments
Click here to see the latest project updates.
-