Newmarket Heights Watermain Lining Project
Consultation has concluded
UPDATE: May 13, 2024
All work has been completed and the project is now in warranty period.
UPDATE: December 2023
The project is substantially complete. Temporary line painting will be completed winter 2023 with final line painting and minor restoration works in spring 2024. Thank you for everyone's patience during construction. If you notice any deficiencies on the project please contact Eric Engman.
The Town of Newmarket has started its watermain lining project in the Newmarket Heights area.
Watermain lining is a method used to renew the current watermain infrastructure in order to increase its lifecycle. As part of this project, the Town will also be replacing the fire hydrants and reconstructing pedestrian crosswalks to meet current accessibility requirements.
Newmarket Heights' residents are encouraged to view the engineering drawings for this project in order to review the potential changes to the boulevard fronting your home. You can also view the map below to see the area where the project will take place.
For the most up-to-date information on the project, follow the news feed below.
Map of construction area
Frequently Asked Questions:
Water is being provided through the temporary above-ground pipes which connect to the hose bibs. These watermain pipes and hoses have been disinfected, certified, protected during transportation, and in compliance with all regulatory standards. All pipes are cleaned and commissioned as per Town of Newmarket standards before connecting to the homes. The water is continually monitored and tested.
Your water meter will be turned off during the duration of the project. The Town of Newmarket has worked Newmarket Hydro and all residents will be billed at a flat rate based on historical use when they are connected to the temporary by-pass. Normal billing will resume when the water meter is turned back-on.
There is a leaking pipe or a safety issue on-site. Who do I contact?
Please call the contractor (Fer-Pal):
- Daytime phone number (7 a.m. to 6 p.m.) 1-866-344-1058
- After hours phone number (6 p.m. to 7 a.m.) 1-855-530-8592
UPDATE: May 13, 2024
All work has been completed and the project is now in warranty period.
UPDATE: December 2023
The project is substantially complete. Temporary line painting will be completed winter 2023 with final line painting and minor restoration works in spring 2024. Thank you for everyone's patience during construction. If you notice any deficiencies on the project please contact Eric Engman.
The Town of Newmarket has started its watermain lining project in the Newmarket Heights area.
Watermain lining is a method used to renew the current watermain infrastructure in order to increase its lifecycle. As part of this project, the Town will also be replacing the fire hydrants and reconstructing pedestrian crosswalks to meet current accessibility requirements.
Newmarket Heights' residents are encouraged to view the engineering drawings for this project in order to review the potential changes to the boulevard fronting your home. You can also view the map below to see the area where the project will take place.
For the most up-to-date information on the project, follow the news feed below.
Map of construction area
Frequently Asked Questions:
Water is being provided through the temporary above-ground pipes which connect to the hose bibs. These watermain pipes and hoses have been disinfected, certified, protected during transportation, and in compliance with all regulatory standards. All pipes are cleaned and commissioned as per Town of Newmarket standards before connecting to the homes. The water is continually monitored and tested.
Your water meter will be turned off during the duration of the project. The Town of Newmarket has worked Newmarket Hydro and all residents will be billed at a flat rate based on historical use when they are connected to the temporary by-pass. Normal billing will resume when the water meter is turned back-on.
There is a leaking pipe or a safety issue on-site. Who do I contact?
Please call the contractor (Fer-Pal):
- Daytime phone number (7 a.m. to 6 p.m.) 1-866-344-1058
- After hours phone number (6 p.m. to 7 a.m.) 1-855-530-8592
-
Watermain Lining Project: Notice 5
Share Watermain Lining Project: Notice 5 on Facebook Share Watermain Lining Project: Notice 5 on Twitter Share Watermain Lining Project: Notice 5 on Linkedin Email Watermain Lining Project: Notice 5 linkDear Resident,
This notice provides an update on the Newmarket Heights Watermain Lining Project and the upcoming works within the culde-
sac of Willow Lane (see map on the reverse side of this notice).
As part of the project, the Town will install a new watermain auto-flusher to enhance water circulation within the water
system. To facilitate this installation, a new catch basin, manhole, and a small new water pipe will be installed, connecting
the existing watermain on Willow Lane to the new auto-flusher (see reverse side of this notice for the approximate
locations).
To install these new features, a trench will be excavated within the roadway and boulevard, causing intermittent traffic
delays and temporary disruptions to driveway access for approximately one week. The contractor plans to start this work
during the week of October 2nd, barring any unforeseen circumstances. The contractor will notify you before the work begins
and provide information about parking impacts. At times you may be asked to park on Willow Lane, north of Longford to
facilitate this work. If you have planned deliveries, events, or accessibility concerns, please contact the undersigned to
coordinate. After the installation of the auto-flusher and related features, the contractor will remove and replace deficient
sections of curb and will proceed to resurface the entire cul-de-sac with new asphalt.
Waste collection will continue as usual, and we remind all residents to place garbage, recycle bins, and green bins out by
7:00a.m.
As with all construction projects, residents may experience dust, noise, and minor vibrations. The Town and contractor will
minimize these inconveniences as much as possible.
Should you have any questions regarding the project prior to or during the work, please contact Eric Engman, Capital
Works Project Manager at the Town of Newmarket, by emailing eengman@newmarket.ca or by calling 905-895-5193 ext.
2519.
-
Watermain Lining Project: Notice 4
Share Watermain Lining Project: Notice 4 on Facebook Share Watermain Lining Project: Notice 4 on Twitter Share Watermain Lining Project: Notice 4 on Linkedin Email Watermain Lining Project: Notice 4 linkSeptember 1st, 2023
Dear Resident,
This letter is to provide an update on the construction work being completed as part of the Newmarket Heights Watermain Lining project that started in July 2023. Work for this project is being implemented in four phases. Please see the map attached for more information as to which phase your property belongs to.
What has been completed to date?
- Installed traffic signage and closed Gwillimbury Road between Lindsay Avenue and Penn Avenue;
- Several pits have been dug around the area;
- Installed temporary above-ground watermain by-pass in phases 1, 2, 3 and 4;
- Most homes in phase 1, 2, and 3 have been connected to the temporary by-pass to ensure you have access to water; and
- Cast iron watermain has been lined in phase 1.
What to expect moving forward?
- Connect the remaining homes in phase 3 and 4 to the temporary by-pass;
- Watermain lining to continue in all phases;
- Installation of new fire hydrants and a new auto-flusher on Willow Lane;
- Sidewalk intersection enhancements; and
- Resurfacing of Willow Lane cul-de-sac (south of Longford Drive).
Frequently Asked Questions:
1) How is the water being provided to my home? Is it safe?
Water is being provided through the temporary above-ground pipes which connect to the hose bibs at your house. These watermain pipes and hoses have been disinfected, certified, protected during transportation, and are in compliance with all regulatory standards. All pipes are cleaned and commissioned as per Town of Newmarket and Provincial standards before connecting to the homes. The water is continually monitored and tested.
2) My water meter is turned-off, how will I be billed for water use?
Your water meter will be turned off during the duration of the project. The Town of Newmarket has worked with NT Power, and all residents will be billed at a flat rate based on historical use when they are connected to the temporary by-pass. Normal billing will resume when the water meter is turned back on, which is anticipated to be in October 2023, as long as there are no unforeseeable delays.
3) There is a leaking pipe or a safety issue on-site. Who do I contact?
Please call the contractor (Fer-Pal):
o Daytime phone number (7:00 a.m. to 6:00 p.m.) 1-866-344-1058
o After hours phone number (6:00 p.m. to 7:00 a.m.) 1-855-530-8592
4) When will the project be completed?
Most of the project is on schedule to be completed by the end of this year, with minor restoration works to occur early in 2024.
As with all construction works, residents may experience dust, noise, and vibration. The Town and its contractor will limit these inconveniences as much as possible.
Should you have any questions regarding the project, please reach out to Eric Engman, Project Manager, Capital Projects, at the Town of Newmarket by emailing eengman@newmarket.ca or by calling 905-895-5193, ext. 2519. We thank you for your patience during this work.
-
IMPORTANT - Temporary Water Service Hook-Up Instructions
Share IMPORTANT - Temporary Water Service Hook-Up Instructions on Facebook Share IMPORTANT - Temporary Water Service Hook-Up Instructions on Twitter Share IMPORTANT - Temporary Water Service Hook-Up Instructions on Linkedin Email IMPORTANT - Temporary Water Service Hook-Up Instructions linkAs part of FER-PAL Infrastructure’s project with the Town of Newmarket, the water main pipe on your street is scheduled to be cleaned and Cured-In-Place Pipe (CIPP) Structurally Lined during the next several weeks. CIPP Structural Lining prevents further pipe corrosion, adds strength, improves fire flow capacity, and helps eliminate discolored water. Essentially, we are building a pipe within a pipe. To learn more about the project, please contact www.heynewmarket.ca/NewmarketHeights
During construction, your home will receive water through an above-ground temporary piping network (by-pass) installed along the curb or ditch line on your street. A hose attached to the temporary by-pass (blue pipe) will be connected to your home with a "Y" connector via the outside hose tap. This allows you to receive water in your home. See photo for operating instructions.
Although several access pits will be excavated along the water main, efforts will be made to avoid excavating in newly paved areas.
From time to time, FER-PAL will have to turn off the water supply to your home. You will be notified in advance of any scheduled interruption in service. However, this may not always be possible, for example, when a water main break occurs. You may also experience rusty water while work is taking place. If this happens, let the water run until it flows clear.
The temporary water supply network and the rehabilitated water main will be disinfected prior to hook up to your home in accordance with the Town of Newmarket Disinfection of Water Main procedures.
FER-PAL recommends that you temporarily disconnect any water treatment system, such as softeners or filters, water-cooled air conditioners or any similar plumbing fixtures, as they may be damaged during construction. As automatic lawn sprinkler systems may not operate properly while the work is taking place, manual watering may be necessary.
Once the water main rehabilitation has been completed, all excavated areas will be restored. In addition, the grassed areas will receive an initial watering by FER-PAL. However, we suggest that you continue to water any grassed areas for 1-2 hours twice a week.
We appreciate your cooperation during this improvement project. Every attempt will be made to minimize interference with local activities. Please exercise caution around construction, equipment, and the temporary water main system.
If you should have further questions regarding this matter, please contact our office at
1-416-742-3713 or toll free 1-866-344-1058
For afterhours emergencies (6:00pm – 7:00am) please contact the following number 1-(855)-530-8592
For daytime emergencies (7:00am – 6:00pm) please contact the following number 1-866-344-1058
-
Watermain Lining Project: Notice 3 - June 30, 2023
Share Watermain Lining Project: Notice 3 - June 30, 2023 on Facebook Share Watermain Lining Project: Notice 3 - June 30, 2023 on Twitter Share Watermain Lining Project: Notice 3 - June 30, 2023 on Linkedin Email Watermain Lining Project: Notice 3 - June 30, 2023 linkDear Resident,
This letter is to provide an update following the Virtual Public Information Centre held on May 31,
2023, for the watermain lining project located within the Newmarket Heights neighbourhood. The Town
of Newmarket has awarded this contract to Fer-Pal Ltd. The project will involve 3.7 kilometers of
watermain lining, fire hydrant replacement, new fire hydrants and sidewalk enhancements.
Preliminary construction work is scheduled to start in July and is expected to last until the late
fall, depending on the weather.
Watermain lining is less obstructive compared to open cutting, removing, and replacing the
watermain. However, residents should still anticipate minor traffic delays due to the construction.
There will be a number of excavated pits in boulevards, roadways, and sidewalks, which will be well
signed and fenced. Please proceed with caution while driving in this area during the construction.
We expect to have a temporary road closure on Gwillimbury Road between Penn Avenue and Lindsay
Avenue as part of this work. A detour route will be in place with signage directing motorists from
Penn Avenue to Lindsay Avenue/Longford Drive. There will be no impact to emergency vehicles or
garbage collection as part of this road closure.
As with all construction works, residents may experience dust, noise and vibration. The Town and
its contractor will limit these inconveniences as much as possible. We also understand that
children may be curious about the construction activities and equipment, so we kindly ask parents
to keep children and pets out of the construction areas, both during and after working hours.
Should you have any questions regarding the project prior to or during the work, please reach out
to Eric Engman, Project Manager, Capital Projects, at the Town of Newmarket by emailing
eengman@newmarket.ca or by calling 905-895-5193 ext. 2519. We thank you for your patience and
indulgence during this work.
To learn more about the project, please visit www.heynewmarket.ca/NewmarketHeights
-
Watermain Lining Project: Notice 2 - May 19, 2023
Share Watermain Lining Project: Notice 2 - May 19, 2023 on Facebook Share Watermain Lining Project: Notice 2 - May 19, 2023 on Twitter Share Watermain Lining Project: Notice 2 - May 19, 2023 on Linkedin Email Watermain Lining Project: Notice 2 - May 19, 2023 linkFurther to our notice sent to you on February 6, 2023, the Town is hosting a Virtual Public Information Centre (VPIC) on Wednesday May 31, 2023 from 7 to 8 p.m. to inform the public of a watermain lining project located within the Newmarket Heights area (location shown on the back of this notice).
The proposed works include cured-in-place-pipe (CIPP) lining of the watermain on these streets, fire hydrant replacement, and the reconstruction of pedestrian crosswalks to meet current accessibility standards. The purpose of the VPIC is to notify the public prior to the start of construction, to review the final drawings and to discuss the scope of work and the expected disruptions from construction.
The itinerary for the VPIC is as follows:
• 7 p.m. – Staff introductions
• 7:10 p.m. – Presentation starts
• 7:30 p.m. – Questions and answers
• 8 p.m. – Adjournment
Representatives from the Town’s Engineering Services Department and the consulting engineer on the project (Ainley Group) will be available to answer any questions you may have. If you are unable to attend the VPIC and want to provide input regarding this project, or if you have additional questions after attending the VPIC, please contact Eric Engman, Capital Works Project Manager, by phone at 905-953-5300 ext. 2519 or by email at eengman@newmarket.ca.
This project is expected to start in June 2023, depending on budget, other priorities and a successful tendering
and contract execution process. The engineering drawings and all notices are available at heynewmarket.ca/NewmarketHeights.
ZOOM LOG-IN INFORMATION
Webinar ID: 929 4966 6708
Passcode: 693497
Phone Number: 647-374-4685 or 647-558-0588
International numbers available: https://townofnewmarket.zoom.us/u/ab1HspghwB
-
Watermain Lining Project: Notice 1 - Feb 06, 2023
Share Watermain Lining Project: Notice 1 - Feb 06, 2023 on Facebook Share Watermain Lining Project: Notice 1 - Feb 06, 2023 on Twitter Share Watermain Lining Project: Notice 1 - Feb 06, 2023 on Linkedin Email Watermain Lining Project: Notice 1 - Feb 06, 2023 linkFebruary 6, 2023
The Town of Newmarket has retained an engineering firm, the Ainley Group, to start the detailed design of a watermain lining project in the Newmarket Heights area.
The purpose of the project is to increase the service life of the watermain, replace the fire hydrants, and reconstruct pedestrian crosswalks to meet current accessibility standards. The anticipated construction start date is summer 2023 pending successful tendering and budget approvals. The Town will provide more information on timing as the design process proceeds. As part of this project, Ainley has reviewed the fire hydrant spacing which resulted in shifting some fire hydrants to new locations in order to conform to the Town’s current engineering design standards.
How to get involved:
The Town will be hosting a Virtual Public Information Centre (VPIC) with residents in the community to discuss the entire project and to answer any questions that you may have. The tentative date for this VPIC is May 2023 and you will receive an invitation to participate in the meeting a few weeks ahead of time.
Who's Listening
-
EE
Phone 905-953-5300 x 2519 Email eengman@newmarket.ca
Engineering Drawings
Upcoming Public Meeting
Project Timeline
-
November 2022 to April 2023 - Engineering Design Process
Newmarket Heights Watermain Lining Project has finished this stageWork on the detailed design of the project begins.
-
Virtual Public Information Centre - May 31st, 2023 7pm
Newmarket Heights Watermain Lining Project has finished this stageZOOM LOG-IN INFORMATION
Webinar ID: 929 4966 6708
Passcode: 693497
Phone Number: 647-374-4685 or 647-558-0588
International numbers available: https://townofnewmarket.zoom.us/u/ab1HspghwB
-
July 2023 - Construction begins
Newmarket Heights Watermain Lining Project is currently at this stage -
Spring 2024 - Construction Complete
this is an upcoming stage for Newmarket Heights Watermain Lining Project